MINISTER, MINISTRY OF DEVELOPMENT OF NORTH EASTERN REGION (SHRI BIJOY KRISHNA HANDIQUE)
(a): The Ministry of DoNER sanctions the developmental projects in North Eastern Region
under Non-Lapsable Central Pool of Resources (NLCPR), Special Bodo Territorial Council (BTC) Package and also through North Eastern Council (NEC). The completion of some of ongoing
projects is delayed beyond target date of completion.
(b): The projects are implemented by State Governments. The main reason for their delay
, inter-alia, includes the restricted working season due to heavy and prolonged rainy season
in the North Eastern Region and limitation of technical & professional expertise. The State-
wise lists of ongoing projects under NLCPR including BTC Package and NEC, where completion is
delayed, along with time overrun, are at Annex-A&B, respectively. Cost overrun due to time
overrun is not admissible under NLCPR scheme whereas no cost overrun due to time overrun is
there in NEC projects.
(c): Monitoring of sanctioned projects is a continuous process. The projects are monitored
regularly through Progress Reports, Utilization Certificates, Photographs and Inspection
Reports of Nodal Officers of the projects submitted by the State Governments from time to
time. Progress of the projects is also assessed in the various review meetings with the
State Governments and field visits carried out from time to time. Chief Secretaries of the
NE States are also responsible for quarterly review of NLCPR projects.
(d): In order to expedite implementation of the delayed projects, the review meetings with
the State Government officers are arranged periodically. Training courses were organised for
the officers of the North Eastern States in project management and implementation. Further,
the earlier Guidelines of NLCPR were studied and amended in the interest of expeditious
implementation of projects.