Question : MUMBAI URBAN TRANSPORT PROJECT PHASE - II



(a) the details of projects in Mumbai Urban Transport project (MUTP) phase-II to be taken up and the approximate expenditure to be incurred thereon, project-wise;

(b) whether the Government of Maharashtra has agreed to share 50% of the projects cost;

(c) if so, the details thereof; and

(d) the time by which the work on the projects are likely to be started?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI BANDARU DATTATRAYA)

(a): It has been decided to take up 10 projects and their components of rolling stock/ resettlement and rehabilitation etc., under Mumbai Urban Transport Project (MUTP) Phase-II. Project-wise details are indicated in the Appendix.

(b) & (c): Government of Maharashtra has agreed to share 50 percent cost of seven projects. Their consent for sharing 50% cost of the remaining three projects is being obtained.

(d): It is planned to take up MUTP Phase-II during 2005-06. However, work on two sanctioned projects is in progress.

APPENDIX

Appendix referred to in reply to para (a) of the Lok Sabha Unstarred Question No. 2490 for answer on 7/8/2003

MUMBAI URBAN TRANSPORT PROJECT (MUTP) (RAIL COMPONENT) PHASE-IIPROJECTS

Sl.	Name of the Project	Cost	Whether
No.	(in	sanctioned	crores	of Rs.)
1. Kurla-CSTM: 5th & 6th Lines 229 No

2. Borivali-Santacruz-Mumbai Central: 6th 294 No Line

3. 12 Car operation on Western Railway - Yes local line #

4. 12 car operation on Central Railway - Yes local line #

5. Bandra-Kurla: East-West Link 480 No 6. Kalyan-Diva: Additional Pair of Lines 110 Yes

7 Diva-Thane: Additional pair of Lines 170 No

8. Extension of Harbour Line: Andheri to 59 No Goregaon

9. DC to AC Conversion: Thane to CSTM 147 Yes 10. S&T upgrade on local lines to improve 240 No headway

Components of above projects
(a) Electric Multiple Unit (EMU) 1672 No procurement/manufacture/retrofitment and maintenance/stabling facilities

(b) Technical Assistance 20 No

(c) Resettlement & Rehabilitation 71 No

(d) Capital Expenditure for Institutional 10 No strengthening
TOTAL 3502

# Work completed. Only rolling stock to be procured. Cost of rolling stock included in component (a) above.