MINISTER OF STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS AND MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI O. RAJAGOPAL )
(a) to (f) : The details of all on-going Railway
projects in Maharashtra and Gujarat, including
outlay proposed for 2002-03 and expected
expenditure upto March, 2002 for each project, is
given in Appendix-I & II respectively. Target date
of completion of projects, wherever fixed, is
given in the status of the project. Projects are
being progressed as per their relative priority
and availability of resources. The steps taken by
the Government for timely completion of these
projects are also given in the Appendices.
The details of surveys in Gujarat and Maharashtra
is in the Appendix-III & IV respectively.
APPENDIX - I
APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (f) OF LOK SABHA UNSTARRED
QUESTION NO. 1736 FOR 14.03.2002
On-going Railway Projects in Maharashtra
S. Name of Rly. Latest Outlay Outlay Status
No. Project Anticip- expected Proposed
ated to end for 2002-
Cost of 2001- 03
02
(Amount in Crores of
Rupees)
New Lines
1 Amravati- CR 175.30 58.30 10.00 Land acquisition is
Narkher in progress.
Earthwork and work
minor and major
bridges are in
progress. Building
work of Amrawati
station building is
nearing completion.
Work is being
progressed as per
availability of
resources.
2 Ahmednagar- CR 353.08 3.45 15.00 Final location
Beed-Parli survey has been
Vaijnath completed for 15 km
from Ahmednagar end
.Tender for final
location survey in
the remaining
stretch has been
processed. Land
acquisition plans &
papers have been
submitted to the
State Govt. for 15
Kms. stretch. The
work would be
progressed once the
land becomes
available. Station
building at Beed is
also in progress.
3 Panvel-Karjat CR 106.90 59.41 20.00 All land has been
: Electrified acquired.
BG Line Earthwork and work
(Phase-I) on bridges are in
progress. Work on
the tunnel is also
in progress.
4 Baramati- CR 75.00 0.43 5.00 Final location
Lonad survey completed.
Preparation of land
acquisition plans
and papers is in
progress.
5 Puntamba- CR 48.78 3.02 10.00 Final location
Shirdi survey has been
completed. Land
acquisition is
being taken
up.Joint survey for
land acquisition is
in progress from
Puntamba end.
Gauge Conversion
6 Miraj-Latur CR 329.02 141.37 30.00 The work is being
progressed in
phases. In the
phase-I, Gauge
conversion work
from Kuruduwadi to
Pandharpur (52 km)
has been completed
. In phase-II, from
Latur Road to Latur
(42 km) earthwork
and major and minor
bridges have been
completed. Track
work has been taken
up and section is
expected to be
completed during
2002-03. Work on
Phase-III, from
Kurduwadi to Latur
(143 km) has also
been taken up.
Miraj-Pandharpur
(137 km) Phase-IV
work will be taken
up as last phase of
the project.
7 Mudkhed- SCR 142.22 7.98 30.00 The work was taken
Adilabad up under BOLT
scheme . Now it has
been decided to
take up the work
through Railway
funding.
Arrangements are
being made to take
up the work.
8 Solapur-Gadag SCR 262.05 136.61 20.00 The work is being
done in phases. The
work Solapur-Hotgi
and Hotgi to
Bijapur has been
completed. Work is
in progress on rest
of section from
Bijapur to Gadag
which will be
completed in the
coming years as per
availability of
resources. Funding
through KRIDES is
being tried with a
view to expedite
early completion of
this work.
9 Secunderabad- SCR 287.83 88.20 30.00 The work has been
Mudkhed & taken up in first
Jankhampet- phase from Mudkhed-
Bodhan Nizamabad (96 Km).
On Mudkhed-
Nizamabad section,
conversion block
has been taken up
and Mudkhed-
Dharmabad is
expected to be
completed by
31.03.2002 and the
rest by 30.06.2002.
Work on the
remaining section
is also in
progress.
10 Akola-Purna SCR 228.00 0.44 10.00 Final Location
Survey is in
progress.
Arrangements are
being made to take
up earthwork and
bridges in first
section from Purna
to Hingoli (81.5
km) .
11 Gondia- SER 242.09 241.89 0.01 The work has been
Chandafort completed.
Financial
adjustments are
being made.
Doubling
12 Daund-Bigwan CR 46.90 44.61 0.50 Work completed and
section
commissioned during
2001-02.
13 Diva-Vasai CR 160.00 152.04 0.50 Work completed and
section
commissioned.
14 Panvel-Roha- CR 4.10 2.60 0.50 FLS completed. Land
Land acquisition is in
acquisition progress and is
likely to be
acquired shortly.
15 Diva- Kaylan CR 48.06 9.98 25.00 Earthwork and
doubling of Bridges in Diva
5&6 line Kalyan are being
taken up. Plans are
under approval.
Tenders for
earthwork and
bridges have been
processed.
16 Panvel-Jasai- CR 53.25 0.001 3.12 Final location
Jawaharlal survey has been
Nehru Port completed. Detailed
Trust (JNPT) planning has been
taken up.
17 Pakni-Solapur CR 33.33 0.00 5.00 New work included
in the Budget 2002-
03.
Metropolitan Transport Projects
18 Kurla-Thane CR 95.00 69.76 10.00 Work of earthwork,
5th & 6th supply of Ballast,
line (Phase- Track linking,
I) Major Bridges,
Foundation and
erection of OHE
structures and
other works are in
progress in
stretches which are
free from
encroachments.
19 Thane-Turbhe- CR 131.47 93.14 1.00 Civil works for
Nerul/ Vashi second line are
part of nearing completion.
corridor No.2 Electrification and
in Navi signaling works are
Mumbai in progress. Delay
in acquisition of
land is affecting
the progress of
work.
20 Belapur- CR 92.50 84.38 0.50 Double line has
Panvel been commissioned
Doubling and opened for
commuter traffic on
14-4-2000.Balance
works to be
executed by CIDCO
are in progress.
21 Belapur- CR 163.49 42.39 1.00 Work of important
Seawood-Uran bridge on Panvel
: Electrified creek ,construction
line of minor bridges
,sub way at Seawood
and work at Sanpada
carshed are in
progress. Due to
financial crunch
being faced by
CIDCO, execution of
the project has
been divided in two
phases. Under first
phase single line
will be laid in the
section.
22 Kurla-thane CR 56.79 30.24 10.00 Earthwork, supply
5th and 6th of Ballast,
line (Bhandup Bridges and 22 kV
to Thane) aerial feeder
Phase-II obstructing 5th and
6th line by
underground cable
between Bhandup-
Mulund and Mulund-
Thane section is in
progress.
23 Thane-Mumbra CR 49.34 1.09 0.10 Detailed survey
5th and 6th report is under
line process for
submission to
Planning Commission
for appraisal.
24 Borivali- WR 401.66 94.59 118.00 Work for earth
Virar : work, major & minor
Quadrupling bridges yard
remodelling and
quarters is in
progress.
25 Santacruz- WR 89.30 88.59 0.40 Work on all minor
Borivali : and major bridges
5th line have been
completed. Work
which was held up
at certain
locations due to
delay in removal of
encroachment, has
been restarted.
Borivali-Andheri
section has already
been commissioned.
Balance section is
expected to be
completed by March,
2002.
26 Virar-Dahanu WR 29.09 26.57 1.00 Work is expected to
Road : be completed
Autoblock shortly.
Signalling
27 Virar Dahanu WR 17.09 14.57 1.00 Project has
Road - recently been
Development cleared from
of facilities Planning
for Commission.
introduction Execution of work
of EMUs and is in progress.
terminal
facilities at
Dahanu Road
Railway Electrification
28 Udhna-Jalgaon WR 140.99 108.90 30.00 93 RKM has been
energised till
Mar` 2001. The work
is progressing as
per schedule .
Target is March
2003.
APPENDIX - II
APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (f) OF LOK SABHA UNSTARRED QUESTION NO.
1736 FOR 14.03.2002
On-going Railway Projects in Gujarat
S. Name of Rly. Latest Outlay Outlay Status
No. Project Anticip- expected Proposed
ated to end for 2002-
Cost of 2001- 03
02
(Amount in Crores of Rupees)
New Lines
1 Kapadvanj- WR 61.67 59.36 0.01 Work has been
Modasa completed.
2 Godhra-Indore WR 597.00 48.73 22.10 This work is being
Dewas-Maksi executed in phases.
The first phase work
between Dewas & Maksi
is now in progress.
Maksi - Dewas section
is targeted for
completion during 2001-
02.
3 Gandhinagar- WR 52.00 0.02 10.00 Final location survey
Adrej Moti- has been completed.
Kalol Further arrangements
are being made to take
up the work.
Gauge
Conversion
4 Viramgam- NR 244.74 1.25 15.00 This work was
Jodhpur BG sanctioned in 1990-91
rail route, as a part of Kandla-
Bhildi-Samdri Bhatinda rail link.
GC of Samdari- The work have been
Luni recently defrozen.
Preliminary arrangement
are being made to
take up the work.
5 Bhildi WR 134.80 15.89 1.00 In Phase-I, work has
(Mehsana- been taken up on
Patan)- Viramgam-Mehsana
Viramgam section. Earthwork,
minor & major bridges
are in progress.
Substructure of all
major and minor bridges
have been
completed.Permanent Way
and signalling of this
section is proposed to
be taken up under BOT
for which tenders are
being processed.
6 Phulera-Marwar- WR 632.35 623.35 9.00 Work has been completed
Ahmedabad and commissioned.
Residual works are in
progress.
7 Rajkot-Veraval WR 291.61 37.32 35.00 Earthwork, minor and
incl. Material major bridges are in
modification progress. Rajkot-
for extn. From Jatalsar is targetted
Wansjaliya - for completion during
Jetalsar 2002-03.
8 Gandhidham- WR 50.75 44.40 0.01 The work has been
Bhuj completed.
9 Wankaner-Malia WR 100.85 100.35 0.01 The work has been
Miyana completed and
commissioned.
10 Surendernagar- WR 227.63 73.99 25.90 The work of conversion
Bhavnagar, of main line from
Dhola-Dhasa- Surendranagar to Rajula
Mahuwa with with connectivity to
the extension Pipavav is to be done
to Pipavav through SPV consisting
of Ministry of Railways
and GPPL for which MOU
has been signed.
Earthwork, bridge work,
ballast supply, etc.
are in progress. The
conversion of
Surendranagar to Rajula
with extension to
Pipavav is targetted
for completion during
2002-03.
11 Dharangadhara- WR 3.39 3.38 0.01 This work is being
Kuda siding done on 1/3rd cost
sharing basis with Co-
sharers are Ministry of
Railways, Gujarat
Government and the
Ministry of Industry.
Formation work
completed and linking
is in progress. Work is
expected to be
completed during 2001-
02.
12 Gandhidham- WR 370.74 14.36 10.00 Preliminary
Palanpur arrangements have been
made to take up the
work. Govt. of Gujarat
has shown willingness
to share part cost of
the project along with
other beneficiaries.
This is being
processed.
Doubling
13 Surat-Kosamba WR 49.00 0.30 16.38 Preparation of plans
PH-I of 3rd and detailed estimate
line between has been taken up.
Vadodara and
Virar
Railway
Electrificati
on
14 Udhna-Jalgaon WR 140.99 108.90 30.00 93 RKM has been
energised till Mar`
2001. The work is
progressing as per
schedule . Target is
March 2003.
APPENDIX - III
APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (f) OF LOK SABHA UNSTARRED
QUESTION NO. 1736 FOR 14.03.2002
S. Name of the Project Rly. Kms.
No.
On-going Surveys in Maharashtra
New Lines
1 Chinchwad and Roha CR 95
2 Solapur-Tuljapur-Osmanabad CR 60
3 Umrer to Nagpur via Khaperkheda CR 45
and Koradi
4 Rotegaon-Punthamba CR 40
5 Kurla-Mahul CR
6 Shirpur-Mhow CR 185
7 Khandwa to Nardana via Khargone, CR 225
Sendhwa
8 Latur Road-Mudkhed SCR 120
9 Ramtek to Gotegaon via Khawasa, SER 240
Seoni and Dhuma
10 Goregaon-Borivali WR 7
Gauge Conversion
11 Pulgaon-Arvi GC with extn. to CR 154
Amla
12 Naghbir to Nagpur SER 126
13 Umrer to Nagbhir SER 90
14 Chhindwara-Nainpur SER 140
15 Chhindwara â Nagpur SER 150
Doubling
16 Daund â Manmad with CR 238
electrification
17 Kalyan-Kasara 3rd line. CR 67
18 Daund-Bigwan-Gulbarga CR 272
19 Mumbai Central-Boravali 5th and WR 30
6th line
S. Name of the Project Rly. Kms. Status
No.
Completed Surveys in Maharashtra in last 5 years where works have not been taken up
New Lines
1 Warora and Umrer CR 106 Completed & project shelved.
2 Kopargaon to Shirdi. CR 17 Completed & project shelved.
3 Dhule-Nardana-Shirpur CR 62 Completed & project shelved
4 Pune-Nasik CR 265 Completed & project shelved
5 Kalyan to Ahmednagar via Murbad CR 240 Completed & project shelved
6 Wardha-Pusad-Nanded CR 260 Completed & under examination
7 Jalna-Khamgaon CR 155 Completed & project shelved
8 Manmad-Dhule via Malegaon CR 98 Completed & project shelved
9 Nasik-Kopargaon via Shirdi CR 92 Completed & project shelved
10 Diversion of Bhusawal-Nagpur CR 20 Completed & project
including Amravati shelved
11 Balharshah-Ashti-Surajgarh CR 20 Completed & project shelved
12 Bandra-Kurla CR 5 Completed & project shelved
13 Beed-Jalna SCR 111 Completed & project shelved
14 Ghatnandur-Ambajogai SCR 21 Completed & project shelved.
15 Kolhapur to Ratnagiri on Konkan SCR 211 Completed & project
Rly via Talwade shelved .
16 Parli Vaijnath-Ghatnadur SCR 25 Survey dropped
17 Wadsa-Godchhiroli SER 50 Completed & project shelved
18 Nagpur-Bhairamgarh SER 247 Completed & project shelved
19 Dahanu Road â Nashik Road WR 168 Completed & project shelved.
Gauge Conversion
20 Pachora-Jamner GC with extension CR 104 Completed & project
upto Ajanta caves shelved.
21 Purna-Akola-Khandwa-Ratlam-Mhow WR 625 Completed & project sanctioned from Purna-Akola in 2000-01.
Doubling
22 Pune-Lonavla Quadrupling CR 64 Completed & project shelved
23 Panvel-Pen-Roha CR 76 Completed, Report under examination
24 Kolhapur-Pune SCR 326 Completed & project shelved
25 Nardana-Amalner WR 28 Completed & project shelved
APPENDIX - IV
APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (f) OF LOK SABHA UNSTARRED
QUESTION NO. 1736 FOR 14.03.2002
S. Name of the Project Rly. Kms.
No
.
On-going Surveys in Gujarat
New Lines
1 Bhavnagar-Tarapur WR 150
2 Kharaghoda-Santalpur WR 100
3 Connecting Nadiad-Kapadwanj- WR 22
Modasa with Udaipur
4 Jaisalmer to Kandla WR 600
Gauge Conversion
5 Mehasana-Taranga Hill WR 57
6 Udaipur City-Himmatnagar- WR 346
Ahmedabad
Doubling
7 Delhi-Ahmedabad WR 934
8 Udhna- Jalgaon WR 295
S. Name of the Project Rly. Kms. Status
No
Completed Surveys in Gujarat in last 5 years where works have not been taken up
New Lines
1 Ranu-Pipri-Bhadran WR 29 Completed & project included in the 3rd line for Virar-Ahmedabad.
2 Veraval to Kodinar WR 36 Completed & project shelved
3 Kodinar to Pipavav coastal WR 99 Completed & project
line. shelved
4 Dahanu Road â Nashik Road WR 168 Completed & project shelved.
5 Porbander to Porbander port WR 5 Completed & project shelved
6 Mobha Road-Bhadran WR 29 Completed & project shelved
Gauge Conversion
7 Bharuch-Samni-Jambusar- WR 96 Completed & project
Veshwamitri shelved
8 Bharuch-Samni-Dahej WR 62 Completed & project shelved
9 Jambusar â Kavi WR 26 Completed & project shelved
10 Bhadran-Bochasan-Ptelad-Nadiad WR 59 Completed & project shelved
11 Miyagam-Karjan-Daboi-Samlaya WR 80 Completed, included in the 3rd line for Virar Ahmedabad.
12 Bhuj-Neliya WR 101 Completed & project shelved.
13 Kalol-Kotasan WR 37 Completed. Report under examination.
14 Pratapnagar to Chhota Udaipur WR 250 Completed. Report
Gauge conversion and new BG under examination.
line from Chhota Udaipur to
Dhar
Doubling
15 Virar & Ahemdabad. 3rd line WR 549 Completed & project shelved.