Question : Railway Projects through BuildOperate-Transfer Model

(a) whether the railways has identified some projects to be taken up for development through the new Build-Operate-Transfer (BOT) annuity model;

(b) if so, the details of the projects;

(c) whether the feasibility study of the proposed projects has since been completed and if so, the details thereof;

(d) the details of the developers identified to whom this task is likely to be handed over; and

(e) the time by which the projects under BOT are likely to be completed?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS

(SHRI MANOJ SINHA)

(a): Yes, Madam.

(b) & (c): Three (03) projects have been identified for execution under Build-Operate-Transfer (BOT) Annuity model. Feasibility study of these projects have been completed and the details are as under:-

(i) Bhadrak-Nargundi 3rd line (80 km)- East Coast Railway – Estimated project cost: ? 900 crore.

(ii) Kazipet-Vijayawada 3rd line with electrification (202 km)- South Central Railway - Estimated project cost: ?1566 crore.

(iii) Nagpur-Wardha 3rd line (76 km)- Central Railway - Estimated project cost: ? 550 crore.

(d) & (e): No concessionaire has been appointed for the above mentioned annuity projects. As such, no time frame for completion can be indicated.

*****