MINISTER OF STATE IN THE MINISTRY OF RAILWAYS(SHRI R. VELU)
(a)to(g): A statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (g) OF THE UNSTARRED QUESTION NO. 420 BY SHRI FAGGAN SINGH KULASTE TO BE
ANSWERED IN LOK SABHA ON 28.02.2008 REGARDING GAUGE CONVERSION AT JABALPURâNAINPUR BALAGHAT RAILWAY LINE.
(a): Earthwork and bridgeworks have been taken up, wherever land is available along BalaghatâNainpurâJabalpur section.
Besides, traffic block has been imposed on BalaghatâKatangi section for gauge conversion work. The work is being progressed
as per availability of resources.
(b): State Government is being actively pursued to expedite handing over of possession of the balance land to the Railways
so that the work on the detour alignment can be taken up. Besides, gauge conversion of BalaghatâKatangi is targeted for
completion during 2008â09.
(c): Yes, Sir. Demands have been received occasionally from some of the elected public representatives for conversion of
the existing NainpurâMandla Fort narrow gauge section into broad gauge.
(d)&(e): Preparation of an updated combined survey report for gauge conversion of ChhindwaraâNainpur and NainpurâMandla
Fort sections has been taken up. Baba Dhaniram Ashram is located at about 2.5 Kms away from Mandla station and is
well-connected by road from the existing station.
(f)&(g): Budget allotments for various new/ongoing works are made as per their operational priorities and overall
availability of resources. An outlay of Rs. 60 crore has been provided for this work in the Budget 2007â08 and an outlay of
Rs. 60 crore has been proposed for this work in the Budget 2008â09.