(a) to (e): A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PART (a) TO (e) OF LOK SABHA STARRED QUESTION NO.401 BY
DR. MURLI MANOHAR JOSHI AND SHRI ANANT KUMAR HEGDE FOR ANSWER ON 08.12.2010 REGARDING
MOBILISING FUNDS THROUGH PPP-MODEL.
(a): The strategy for infrastructure development in the Eleventh Plan reflects the dominant
role of the public sector in building infrastructure. However, it also recognizes that the
quantum of resources required to meet the deficit in infrastructure exceeds the capacity of
the public sector. It is, therefore, necessary to attract private investment through
appropriate forms of Public Private Partnerships (PPP) to meet the overall investment
requirements.
The relative role of the public and private sectors will vary. In some sectors such as
irrigation and water resources management, construction of rural roads, capital dredging
at major ports, as well as in certain economically or situationally disadvantaged regions,
the bulk of the investment in infrastructure would have to come from the public sector.
Available public sector resources must therefore be directed to these sectors as a matter
of priority. Precisely for this reason, PPPs must be seriously explored in other areas.
The strategy for the Eleventh Plan encourages private sector participation directly as well
as through various forms of PPPs where desirable and feasible.
(b): The total investment in Infrastructure during the Eleventh Plan period is projected at
Rs. 20,56,150 crore. The investment projected in each of the ten major physical infrastructure
sectors over the Eleventh Five Year Plan Period is as follows:
Rs. crore at 2006-07 price
SL.NO SECTORS PROJECTED INVESTMENT Centre State Private Total
1 Electricity (incl. NCE) 255316 225697 185512 6,66,525
2 Roads and Bridges 107359 100000 106792 3,14,152
3 Telecommunication 80753 - 177686 2,58,439
4 Railways(incl. MRTS) 201453 10000 50354 2,61,808
5 Irrigation (incl. Watershed) 24759 228543 - 2,53,301
6 Water Supply and sanitation 42003 96306 5421 1,43,730
7 Ports 29889 3627 54479 87,995
8 Airports 9288 50 21630 30,968
9 Storage 4476 6713 11189 22,378
10 Gas 10327 - 6528 16,855
Total 765622 670937 619591 20,56,150
(c): The Governmentâs strategy of growth with inclusiveness provides high priority to the
social sectors, especially education and health. While these efforts will have to be primarily
in the public sector, there may be merit in bringing in private investment in the social sector
through various forms of Public Private Partnerships. In view of the above, PPP models are
being developed in health and education sectors with the objective of providing access to
the underprivileged sections of the society to quality services at affordable rates.
Development of viable models would lead to private investment through PPPs in the social
sector.
(d) : The Eleventh Plan document states that during the plan period experience of PPP
initiatives in selected states under health sector would be studied. Based on evidence,
efforts would be made to develop a generic framework for different categories of PPPs at
primary, secondary and tertiary levels of health care to improve cost effectiveness, enhance
quality and expand access through extensive stake holder consultations. Setting up of
diagnostic and therapeutic centres by private players in hospital premises would be encouraged.
Emphasis would be on model contractual agreements with specific performance requirements to
be measured by civil society. The Eleventh Plan aims to establish 60 medical colleges and
225 new nursing and other colleges in deficit States through PPP. In the education sector
the Plan envisages setting of 2500 secondary schools in the PPP mode.
(e): As a part of the Mid Term Appraisal of the Eleventh Plan, the Planning Commission has
assessed the investment in infrastructure during the first two years of the Plan and also
revised the projections of investment for the entire Plan period based on available data.
The revised projection of investment for the Eleventh Plan is Rs. 20,54,205 crore, which
is almost equal to the initial target of Rs. 20,56,150 crore.
The projections and the achievement in the first three years of the plan is as under:
Years 2007-08 2008-09 2009-10
Projections 2,70,273 3,21,579 3,89,266
Achievement 3,03,807 3,59,192 4,02,829 (Actual) (Actual) (Proj.)
According to the information available in the Planning Commission the list of PPP projects in
Health, Education and Water supply/ sewerage under implementation by the State Governments may
be seen at Annexure- A & B.