Question : NUCLEAR POWER PROGRAMME .



(a) whether the Government is very keen to implement the third stage of Indian Nuclear Power Programme;

(b) if so, the details thereof and the salient features of the programme;

(c) the list of nuclear power projects initiated during the last five years and to be initiated in the near future; and

(d) the amount earmarked for this programme and the estimated power likely to be generated?

Answer given by the minister



THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS AND PRIME MINISTER’S OFFICE (DR.JITENDRA SINGH):

(a)&(b) The Government is committed to implement the third stage of Indian Nuclear Power Programme, after an adequate nuclear installed capacity has been reached based on Fast Breeder Reactors to be set up in the second stage. On account of non-existence of any fissile isotope in naturally occurring Thorium (unlike that existing in Uranium), commercial utilisation of Thorium, on a significant scale, can begin only when abundant supply of either Uranium or Plutonium resources are available. Upon the launch, followed by a significant growth of a thorium based nuclear programme in this manner, it could be possible to maintain the achieved level (without much further growth) of nuclear power programme with thorium alone, without additional demands on uranium or plutonium resources. Therefore, considering the meager domestic uranium resources in the country, it is feasible to start a significant commercial level Thorium based reactor programme in our country only after an adequate inventory of Plutonium becomes available from our Fast Breeder Reactors, comprising the second stage of Indian nuclear programme. Accordingly, the utilisation of Thorium as a practically inexhaustible energy source has been contemplated during the third stage of the Indian nuclear programme, which can be reached after a few decades.

Substantial work has been carried out in the areas of research on technologies for utilisation of Thorium in nuclear fuel cycle, and on the development of an Advanced Heavy Water Reactor (AHWR), to serve as a technology demonstrator for use of thorium based fuel on a large scale.

(c) & (d) The details are given below:

Projects initiated in the last five years:

 
Project Location Capacity Completion (MW) Cost (`crore) Kakrapar Atomic Kakrapar, Gujarat 2 X 700 11459 Power Project Units 3&4 (KAPP 3&4) Rajasthan Atomic Rawatbhata, 2 X 700 12320 Power Project Units Rajasthan 7&8 (RAPP 7&8)


The details of Nuclear Power Projects planned for start of work in the XII Five Year Plan are given below:
 
Project Location Capacity (MW)
Indigenous Reactors
Gorakhpur Haryana Gorakhpur, Haryana 2 x 700 Anu Vidyut Pariyojana (GHAVP 1&2) Chutka Madhya Chutka, Madhya Pradesh 2 x 700 Pradesh Atomic Power Project (CMPAPP 1&2) Mahi Banswara, 1&2 Mahi Banswara, Rajasthan 2 x 700 Kaiga 5&6 Kaiga, Karnataka 2 x 700 Fast Breeder Kalpakkam, Tamil Nadu 2 x 500 Reactor (FBR 1&2)
Advanced Heavy Location to be decided 300 Water Reactor (AHWR)
Reactors with Foreign Cooperation
Kudankulam Nuclear Kudankulam, Tamil Nadu 2 x 1000 Power Project (KKNPP 3&4) Jaitapur Nuclear Jaitapur, Maharashtra 2 x 1650 Power Project (JNPP 1&2) Kovvada, 1 & 2 Kovvada, Andhra Pradesh 2 x 1500
Chhaya Mithi Chhaya Mithi Virdi, Gujarat 2 x 1100 Virdi, 1&2
The approved cost of Gorakhpur Haryana Anu Vidyut Pariyojana (GHAVP) 1&2 is `20594 crore and that of KKNPP 3&4 is `39849 crore. The cost of the other planned projects under XII Five Year Plan is yet to be finalised.