Question : MULTI-PURPOSE PROJECTS OF STATES



(a) the name of multi-purpose projects under implementation in States including Bihar and Jharkhand;

(b) the total hectare of land which will be irrigated after completion of Auranga Reservoir Project, Kanhar Reservoir Project, Kadhavan Reservoir Project and Kutaku North Reservoir Project of Jharkhand and total area of land to be submerged;

(c) the estimated cost and revised cost of the said projects;

(d) the amount required for generating electricity from Kutaku Reservoir Project in Latehar district of Jharkhand; and

(e) by when the generation of electricity will be started and quantum thereof?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES (SHRI JAI PRAKASH NARAYAN YADAV)

(a) The name of multi-purpose projects under implementation in the States including Bihar and Jharkhand are given in the statement enclosed.

(b) The ultimate irrigation potential of Auranga Reservoir Project, Kanhar Reservoir Project, Kadhavan Reservoir Project and Kutaku North Reservoir Project is 882.97 thousand hectare and 44,706 hectare area will be submerged by these projects.

(c) The estimated cost and revised cost of these projects is given in the statement-II enclosed.

(d) & (e) The hydro-electric component of the Kutaku Reservoir Project with installed capacity of 2 x 12 Mega Watt was cleared by the Central Electricity Authority, Ministry of Power for Rs. 21.94 crore during June, 1983. The Project is scheduled for completion beyond Tenth Five Year Plan.

Statement referred to in reply to part (a) of Lok Sabha Unstarred Question No. 751 for answer on 6.12.2004 regarding Name of Multipurpose Projects in States


 S.No Name of Name of Project state 1 Andhra 1. Nagarjuna Sagar Pradesh 2. Singur 3. Srisailam 2 Bihar 1. Gandak 3 Jharkhand 1. North Koel reservoir 2. Subernarekha 3. Tilaiya Dhadhar Diversion 4 Gujarat 1. Sardar Sarovar 5 Karnataka 1. Tungabhadra 2. Varahi 6 Kerala 1. Kallada 2. Idamalayar 7 Madhya 1. Bansagar Pradesh 2. Bargi (Rani Avanti Bai Sagar) 3. Indira Sagar 4. Hasdeo Bango 5. Pench 6. Rajghat 8 Maharashtra 1. Tillari 2. Warba 3. Dudhganga 4. Bhatsa 5. Surya 6. Krishna Koyana 9 Orissa 1. Potteru 2. Rengali 3. Upper Kolab 4. Upper Indravati 10 Punjab 1. Shahpur Kandi Dam 11 Rajasthan 1. Mahi Bajaj Sagar 2. Jakham 3. Bisalpur 12 Uttaranchal 1. Lakhwar Vyasi 2. Tehri 3. Kishau Dam 13 West Bengal 1. Teesta Barrage
Statement - II
Statement referred to in reply to part (c) of Lok Sabha Unstarred Question No. 751
for answer on 6.12.2004 regarding Name of Multipurpose Projects in States.
Sl.	Name of the	Estimated Cost
NO.	project in	(in Rs. crore)	Jharkhand State	Original	Latest
1.	Auranga Res.	125.40	914.24	Project
2.	Kanhar Res.	Unapproved	1350.00	Project
3.	Kandhavan Res.	Unapproved	1111.14	Project	(1996 price level)
4.	North Koel Res.	439.00	836.11	Project (IS	with Bihar) at	Kutku village	in district	Latehar