THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES(SHRI VINCENT H. PALA)
(a) & (b) Irrigation is a State subject and planning,
execution and funding of the irrigation projects including
priority of execution is within the purview of the concerned
state government. Central Government provides financial
assistance under the Accelerated Irrigation Benefits Programme
(AIBP) to expedite completion of the ongoing irrigation projects.
The status of the major/medium irrigation projects of Maharashtra
under AIBP is given in Annex-I.
(c) Generally the reasons for delay in completion of the
projects are land acquisition problems, resettlement and
rehabilitation problems, contractual problems, geological
surprises, litigations, works to be taken up by other agencies
such as construction of railway crossing, road crossing etc.
(d) The details of funds released so far to the major and medium
projects of the Maharashtra state are given in Annex-I.
(e) Receipt of AIBP release proposal and their processing
and release of funds for the eligible proposals is a continuous
process taken up by the Ministry of Water Resources during the
year. During the 2009-10, grant amounting to Rs.905.505 crore has
been released to Government of Maharashtra under AIBP for
eligible proposals of 2009-10. The details are given in Annex-I.
(f) The Ministry of Water Resources and Central Water Commission
consistently monitors performance of the AIBP assisted projects
from time to time and suggest remedial measures for expeditious
completion of the projects. Since December 2006, the format of
the Memorandum of Understanding (MOU) to be signed by the state
Governments with the Union Government for funding of irrigation
projects under AIBP contains year wise targets of creation of
irrigation potential under AIBP. The guidelines for AIBP provide
that if targeted potential during the year is not created, the
next installment of grant is to be released only on achieving
target. The MOU also contains target dates of completion.
However, there are cases where project completion gets delayed
due to reasons beyond the control of the state governments. In
such a cases, the extension of time is required to be granted.