Question : PERFORMANCE OF PSUS



(a) the performance of Public Sector Undertakings under his Ministry for which Memorandum of Understandings have been signed recently during the current year;

(b) the details of achievements made during the period by these PSUs, PSU-wise so far; and

(c) the details of the ongoing and new power projects proposed by PSUs in power sector cleared/under consideration alongwith their present status, project-wise?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF POWER

( SHRIMATI JAYAWANTI MEHTA )

(a) : These are six MoUs signing Public Sector Undertakings under the Ministry of Power. The performance of each PSU in 1998-99 was as under:

Name of PSU	MoU rating
(1) NTPC Excellent (2) NHPC -Do- (3) Powergrid -Do- (4) PFC -Do- (5) REC -Do- (6) NEEPCO Very Good
Evaluation of performance for the year 1999-2000 is underway.

(b) : Details of achievements during 1998-1999, PSU-wise are at Annexure-I.

(c) : Details of major ongoing and new power projects proposed by PSUs alongwith their present status are at Annexure-II.

ANNEXURE-I

ANNEXURE REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO.6319 TO BE ANSWERED IN THE LOK SABHA ON 8.5.2000 REGARDING PERFORMANCE OF PSUs.

1998-99
1. National Thermal Power Corporation (NTPC) :
Net Profit after Tax - Rs 2815.73 crores Generation - 1,09,500 Million Units
2. National Hydro Electric Power Corporation (NHPC) : Net Profit after Tax - Rs 305.30 crores Generation - 9,917 Million Units
3. North Eastern Electric Power Corporation Ltd (NEEPCO) : Net Profit after Tax - Rs 58.22 crores Generation - 1935.93 Million Units
4. Power Grid Corporation of India Ltd (PGCIL) :
Net Profit after Tax - Rs 444.42 crores Circuit kilometers - 3444 Line Availability - 98.64 %
5. Power Finance Corporation (PFC) :
Net Profit after Tax - Rs 541.36 crores Loans Sanctioned - Rs 3338.75 crores Loans Disbursed - Rs 2467.00 crores
6. Rural Electrification Corporation (REC) : Net Profit after Tax - Rs 299.24 crores Loans Sanctioned - Rs 2878.73 crores Loans Disbursed - Rs 2202.60 crores
ANNEXURE-II

ANNEXURE REFERRED TO IN REPLY TO PART (c) OF UNSTARRED QUESTION NO.6319 TO BE ANSWERED IN THE LOK SABHA ON 8.5.2000 REGARDING PERFORMANCE OF PSUs.

DETAILS OF SOME OF MAJOR ONGOING CENTRAL SECTOR POWER PROJECTS
Sl	Name of Projects	Commissioning	No.	Schedule date
Hydro Projects
1. Dulhasti (3x130 MW) - J&K March, 2002. 2. Dhauliganga (4x70 MW) - U.P. 2004-05. 3. Chamera (St.II)(3x100 MW)- H.P. 2004-05. 4. Koel Karo (4x172.5 + 1x20 MW), Bihar 8 years from date of start 5. Loktak D/S (3x30 MW) Manipur 2006-07. 6. Teesta St.V (3x170 MW) Sikkim 2006-07. 7. Nathpa Jhakri (6x250 MW) H.P. 2001-02. 8. Tehri St.I (4x250 MW) U.P. 2001-03. 9. Koteshwar Dam (4X100 MW) U.P. 2005-06. 10. Doyang (3x25 MW) Nagaland 2000-01. 11. Ranganadi (3x135 MW) Arunachal Pradesh 2001-02. 12. Tuirial (2x30 MW) Mizoram 2005-07. 13. Kopili St.II (1x25 MW) - Assam 2003-04.
Thermal Projects
1. Faridabad Gas Power Project, Haryana 06,99 - 10/2000 2. Simdhari TPS, Andhra Pradesh 03/2002 - 12/2002. 3. Ramagundam TPP-St.III, Andhra Pradesh 55 months from the date of investment. 4. Farakka STPS St.III, West Bengal Yet to be finalised. 5. Talcher STPP St.II, Orissa 11/2003 - 02/2006 6. Neyveli TPS-I, Tamil Nadu 11/2001 - 05/2002.
Transmission Projects:
Ongoing Projects:
1.Kishenpur-Moga Transmission System December, 2000 2.Nathpa-Jhakri Transmission System December,2000 3.Jallandhar-Hamirpur Transmission System July, 2000 4.Tehri Transmission System March, 2002 5.Eastern-Northern Inter Regional HVDC Link March, 2000 6.400/220 KV Allahabad S/Stn. March, 2001 7.Agartala Transmission System December, 2000 8.Talcher Transmission System June, 2003 9.LD & C Schemes in NR January, 2002 10.LD & C Scheme in SR January, 2002 11.LD & C Schemes in NER April, 2004 12.LD & C Schemes in ER September, 2003

LIST OF MAJOR NEW CENTRAL SECTOR POWER PROJECTS AWAITING INVESTMENT SANCTION BY CENTRAL GOVERNMENT
Sl	Name of the Scheme	Installed Capacity	No.	(MW)	Hydel Projects
1. Parbati HEP St.II, H.P. 4X200 = 800 2. Baglihar HEP, J&K 3X150 = 450 3. Chamera HEP St.II, H.P. 3X100 = 300 4. Teesta St.III HEP, Sikkim 6X200 = 1200 5. Dhaleshwari HEP, Mizoram 3X40 = 120 6. Loktak Downstream HEP, Manipur 3X30 = 90 7. Tehri Dam St.II HEP, U.P. 4X250 = 1000 8. Kameng HEP, Arunachal Pradesh 4x150 = 600 9. Tuivai HEP, Mizoram 3X70 = 210
Thermal Projects
1. Auriya CCPP St.II, U.P. 650 2. Rihand STPP St.- II, U.P. 2X500 = 1000 3. Anta CCGT St.II, Rajasthan 650 4. Kawas CCPP St-II, Gujrat 650 5. Jhanor-Gandhar CCPP St.II, Gujrat 650 6. Ramagundam TPP-III, Andhra Pradesh 1X500 = 500 7. Talcher STPP-II, Orissa 4X500 = 2000 8. Sipat STPP, Madhya Pradesh 3X660 = 1980 9. Kahalgaon STPP St.II 2X660 = 1320
Sl. Schemes Likely Commissioning No. Schedule New Schemes of POWERGRID:
1. Unified Load Despatch & Communication for WR 2003-2004 2. Jamshedpur-Rourkela Grid Strengthening 36 months from approval 3. Talcher-Meramundi Grid Strengthening 36 months from approval 4. LILO of Purnea-Dalkhola July, 2001 5. East-West Inter-Regional Link 36 months from approval 6. LILO of Bongaigaon-Malda line at Siliguri 30 months from approval 7. LILO of Bongaigaon-Malda line at Purnea October, 2002 8. ICT at Jeypore 24 months from approval 9. ICT at Malda 18 months from approval 10. India-Bangladesh T/L 48 months from approval 11. Kolhapur-Ponda 36 months from approval 12. Reactor for Kathalguri 12 months from approval 13. Ranganadi-Ziro 24 months from approval 14. Vijaywada-Nellore-Chennai 24 months from approval 15. System Strengthening-II of SR 30 months from approval 16. NLC Extension March, 2001 17. ICT Nagarjuna Sagar 24 months from approval 18. Ramagundam-III 48 months from approval 19. Kaiga-Extension 36 months from approval 20. ICT-Ballabhgarh 24 months from approval 21. Series Compensators on Kanpur-Ballabhgarh Line 24 months from approval 22. Dhauliganga TL 48 months from approval 23. Vindhyachal Realignment 12 months from approval 24. Talcher-II 48 months from approval 25. Tala HEP-T/L 48 months from approval 26. Kawas-II 24 months from approval 27. Gandhar-II 24 months from approval 28. Auraiya-II 24 months from approval 29. Anta-II 24 months from approval 30. Sipat January, 2000 31. Dulhasti Phase-II March, 2002 32. Chamera-II 48 months from approval