(a) whether environment clearance to the Srinagar Hydropower Project has been given for a
63 metre high dam;
(b) if so, whether the developer is making a 90 metres high dam;
(c) if so, whether Ministry modified the Environment Clearance to the project and allowed
making of 90 metre high dam;
(d) if so, the reasons therefor; and
(e) if not, the action Ministry proposes to take if the project is illegally making a
90 metre high dam?