(a) Details of projects completed during the last three years and the current year in the State of Madhya Pradesh is as under:-
Year Sanctioned Completed
No. of Roads No. of LSBs No. of Roads* No. of LSBs
2017-18 913 233 1692 52
2018-19 1 236 859 140
2019-20 112 31 694 171
2020-21 377 167 261 185
TOTAL 1403 667 3506 548
LSB= Long Span Bridge
* Completed Roads includes those sanctioned earlier.
(b) Vertical-wise details of pending works in the State is as under:-
Vertical Sanctioned Completed Balance as on 18.03.2021
No. of Roads No. of LSBs No. of Roads No. of LSBs No. of Roads No. of LSBs
PMGSY-I 18951 659 18846 492 105 167
PMGSY-II 374 245 343 192 31 53
PMGSY-III 485 194 3 4 482 190
RCPLWEA 6 14 0 8 6 6
TOTAL 19816 1112 19192 696 624 416
(c) & (d) Works under PMGSY-I, II and RCPLWEA are pending mainly due to the issues related to forest clearance, availability of land, lack of response to tenders, etc. As reported by State Government, all the pending works under PMGSY-I & II are proposed for completion by March, 2022. Works under RCPLWEA are proposed for completion by March, 2023. Works of PMGSY-III are recently sanctioned and will be completed as per programme guidelines.
*****