Question : Production of Coal

(a) the details regarding all India demand of coal in the last 10 years including current year, year-wise;
(b) the details of production, supply and import of coal by Coal India Limited (CIL) and its subsidiaries during last 10 years including current year;
(c) the details of raw coal production by CIL and its subsidiaries during the last 10 years, subsidiary-wise and year-wise;
(d) the average cost of domestic production of coal and the cost incurred (per Metric tonne) on import of coal from different countries as of now;
(e) whether the coal sector is facing a slow down and if so, the details thereof and the reasons therefor; and
(f) the steps taken by the Government to prevent further slow down?

Answer given by the minister



MINISTER OF PARLIAMENTARY AFFAIRS, COAL AND MINES

(SHRI PRALHAD JOSHI)

(a)&(b): All India actual demand during last 10 years is given below:-
Year All India Actual Demand (MT)
2010-11 592.36
2011-12 638.20
2012-13 712.94
2013-14 738.92
2014-15 821.55
2015-16 836.39
2016-17 836.93
2017-18 898.55
2018-19 969.47
2019-20 1000.00#
# Estimated







Year-wise production and supply of coal by CIL is given below:
Year Production of coal by CIL (MT) Supply of coal by CIL (MT)
2010-11 431.32 423.78
2011-12 435.84 432.62
2012-13 452.20 464.54
2013-14 462.41 470.92
2014-15 494.23 488.86
2015-16 538.75 534.08
2016-17 554.14 542.98
2017-18 567.36 580.29
2018-19 606.89 608.09
2019-20 517.80 @ 528.30 @
@ upto Feb, 2020

CIL has imported coal only for the year 2014-15 and 2015-16 to the tune of 4.83 Lakhs tones and 3.58 Lakhs tones respectively.
(c): The details of subsidiary wise, year-wise raw coal production by CIL and its subsidiaries during the last ten years is given below:-
(in Million Tonnes)
Co. 2010-11
Actual 2011-12
Actual 2012-13
Actual 2013-14
Actual 2014-15
Actual 2015-16
Actual 2016-17
Actual 2017-18
Actual 2018-19
Actual 2019-20
Actual
ECL 30.80 30.584 33.901 36.05 40.01 40.21 40.52 43.57 50.16 43.90
BCCL 29.01 30.191 31.211 32.61 34.51 35.86 37.04 32.61 31.04 24.34
CCL 47.52 48.024 48.061 50.02 55.65 61.32 67.05 63.40 68.72 55.45
NCL 66.25 66.399 70.021 68.64 72.48 80.22 84.10 93.02 101.50 98.05
WCL 43.65 43.115 42.287 39.73 41.15 44.82 45.63 46.22 53.18 47.07
SECL 112.71 113.834 118.219 124.26 128.27 137.93 140.01 144.71 157.35 127.50
MCL 100.28 103.116 107.895 110.44 121.38 137.90 139.21 143.06 144.15 121.11
NEC 1.10 0.997 0.605 0.66 0.78 0.49 0.60 0.78 0.78 0.38
CIL 431.32 435.860 452.200 462.41 494.23 538.75 554.14 567.36 606.89 517.80

(d): Average cost of production of CIL mines in 2018-19 was Rs.1145.85 per tonne. Cost incurred per tonne on import of coal during 2018-19 was Rs.7764.

(e)&(f): All India coal production achieved a growth of 8.1% in 2018-19. During April 19 –Feb. 20, coal production declined by 0.64% as compared to the corresponding period of the previous year. The decline in coal production is largely due to heavy rainfall witnessed in the coal mining areas in the current year which was around 25% more than the previous year. Further, rains also continued during the month of October. However, production has started showing an upward trend since November, 2019 and the country achieved highest ever production of 74.8 MT in the last five years in January, 2020 and 77.96 MT in February, 2020.

The focus of the Government is on accelerating domestic production of coal through allocation of more coal blocks, pursuing with State Government for assistance in land acquisition and coordinated efforts with Railways for movement of coal.




In order to enhance domestic production, 25% of coal production has been allowed for sale of coal for newly allocated coal blocks.

Further, for sale of coal, allowing 100% FDI for coal mining activities including associated processing infrastructure is expected to attract international players and create efficient and competitive coal market.

In order to enhance coal production, Coal India Limited (CIL) has taken the following steps:

• CIL and its subsidiaries have planned and implemented higher capacity mega mines (Capacity>10MTY) with high mechanization. CIL has identified mines/projects for further capacity expansion plan till 2030.
• Portal based monitoring of on-going projects to ensure timely completion of projects.
• Introduction of Surface Miners in opencast mines to improve operational efficiency and cater to environmental needs. During 2018-19, around 50% of the opencast coal production in CIL was through Surface miners.
• Introduction of Mass Production Technology in underground coal mines: 2 mines are worked with Powered Support Longwall technology and 11 mines are worked with Continuous Miner technology.

****