Question : NERUDP

Will the Minister Of URBAN DEVELOPMENT be pleased to state :-

(a) the details of the North Eastern Region Urban Development Programme (NERUDP) and the amount spent during the last three years under NERUDP, State-wise;

(b) the details of the projects executed for water supply, sewage and sanitation, and solid waste management under NERUDP, State-wise;

(c) whether some of the projects are incomplete and if so, the details thereof along with the time since when these projects are lying incomplete and reasons therefor project-wise; and

(d) the details of the projects that have been sanctioned for the current and coming years?

Answer given by the minister

THE MINISTER OF STATE IN
THE MINISTRY OF URBAN DEVELOPMENT
(SHRI BABUL SUPRIYO)

(a): The Ministry of Urban Development (MoUD) is implementing the North Eastern Region Urban Development Programme (NERUDP) with the financial assistance from Asian Development Bank (ADB) covering capital cities of 5 North Eastern States viz. Agartala (Tripura), Aizawl (Mizoram), Gangtok (Sikkim), Kohima (Nagaland), and Shillong (Meghalaya) for water supply, sewage and sanitation, and solid waste management.

Amount spent during last three years under NERUDP State-wise is as under:
<pre> Rs Crore
State 2013-14 2014-15 2015-16
Nagaland 11.16 33.23 14.90
Mizoram 11.56 61.75 47.74
Meghalaya 2.77 7.56 4.20
Sikkim 12.73 34.21 13.75
Tripura 9.51 55.75 13.95
Total (States) 47.74 192.49 94.54
MoUD 1.04 1.20 1.20
Total 48.77 193.69 95.74
</pre>

(b): The list of projects which have been executed and completed is at Annex – I

(c): The list of projects which are under execution is at Annex – II

(d): The list of projects which have been sanctioned for the current and coming years is at Annex – III


Annex - I
List of the projects which have been executed and completed
<pre>
Sl.No. State City projects
1 Mizoram Aizawl Water Supply : Replacement of 7 water reservoirs, installation of 2 chlorinators and household water meters
2 Sikkim Gangtok Water Supply :
Water distribution netwrok in Burtuk and Chandmari and allied works
3 Tripura Agartala Water Supply : Rehabilitation of 22 tubewells
4 Nagaland Kohima Water Supply :
Replacement of 18 water reservoirs and refurbishment of water treatment plant.
Solid Waste Management : Development of land-fill site including composting plant.
</pre>

Annex – II
List of projects which are under execution
<pre>
Sl.
No. State City Projects under execution
1 Mizoram Aizawl Water Supply :
Construction of 3 water reservoirs, water distribution network in 8 wards and allied works
Solid Waste Management :
Procurement of household bins for waste segregation at source
Sewage and sanitation:
Construction of sewage treatment plant, sewage network, and 10 community toilet blocks.
2 Sikkim Gangtok Water Supply :
Improvement of existing water supply sytem in remaining areas and allied works
Solid Waste Management :
Construction of land-fill site, compost plant, and collection and transportation vehicles
3 Tripura Agartala Water Supply :
Construction of 7 ground water treatment plants, 14 overhead tanks, water distribution system for South Zone, and allied works.
4 Nagaland Kohima Water Supply :
Rehabilitation of water distribution network and allied works
Solid Waste Management :
Waste collection vehicles, equipment, and household bins for waste segregation at source
Sewage & Sanitation :
Septage management unit
5 Meghalaya Shillong Solid Waste Management :
Procurement of collection and transportation vehicles for SMB area, equipment, and household bins for waste segregation at source
</pre>

Annex – III
List of projects which have been sanctioned for the current and coming years
<pre>
Sl.No. State City Projects sanctioned
1 Tripura Agartala Water Supply :
Water distribution network for Central Zone, construction of 14 tubewells
Solid Waste Management, Procurement of collection and transportation vehicles and equipment
Sewage & Sanitation :
Septage treatment plant and equipment
2 Mizoram Aizawl Water Supply:
Augmentation of bulk water including water treatment plant, distribution network in 33 wards including reservoirs, and allied works
Solid Waste Management :
Development of land-fill site, collection and transportation vehicles, composting plants, and other equipment
Sewage and sanitation :
Bio-digestor unit including waste treatment plant, and other equipment
3 Meghalaya Shillong Solid Waste Management Development of land fill site at Martin Extension (Phase-II), replacement of old compost plant and allied works, Procurement of collection and transportation vehicles for outside SMB area