Question : RAILWAY PROJECTS IN TAMIL NADU



(a) the current status of ongoing gauge conversion and laying new rail lines projects pertaining to Tamil Nadu;

(b) whether some of the proposed projects are still awaiting clearance of the Railways;

(c) if so, the details thereof alongwith the reasons for delay in granting clearance in each of such projects and the time by which the clearance is likely to be granted;

(d) the details of amount earmarked and spent for the said projects, project-wise;

(e) the total length of the broad gauge and metre gauge rail line in Tamil Nadu at present; and

(f) the status of new rail lines Ariyalur-Thanjavur, Needamangalam-Pattukottai, Dindigul-Kumili, Dharamapuri-Morappur, Palni-Erode and Tiruvannamalai-Jolarpettai?

Answer given by the minister


MINISTER OF THE STATE IN THE MINISTRY OF RAILWAYS (SHRI K. H. MUNIYAPPA)

(a) to (f): A Statement is attached.