THE MINISTER OF STATE FOR WATER RESOURCES, RIVER DEVELOMPMENT & GANGA REJUVENATION
(Dr. SANJEEV KUMAR BALYAN)
(a) Yes, Madam. The Assam Integrated Flood and River Bank Erosion Risk Management Investment Program (AIFRERMIP-I) Tranche-I has been implemented since 2011-12.
The details of works taken up under Palasbari-Gumi sub-project and Dibrugarh sub-project are as follows:-
(A) Palasbari-Gumi Sub Project:- Three major packages were taken up under this sub-project two at Palasbari reach and one at Gumi reach.
A(i) Palasbari Erosion Project in under water protection works below water level, at a cost of Rs 3511.48 lakhs
A (ii)Construction of Palasbari Embankment with black topped road and slope protection works above low Water Level (LWL) along the Brahmaputra River, at a cost of Rs.3737.52 lakhs
A (iii)Gumi erosion protection works, at a cost of Rs. 3361.15 lakhs
(B) Dibrugarh Sub Project:- Under this subproject two major packages [B (i) and B (ii)] and four other works [B (iii)] were taken up as follows:
B (i) Construction of revetments, geobags apron for Motholla –Oakland Bank protection works along the Brahmaputra rivers, at a cost of Rs. 2760 lakhs
B (ii)Raising, Strengthening, Up-gradation and Construction of Road works for Dibrugarh Town Protection Dyke, at a cost of Rs. 2979.1 lakhs.
B (iii)Fabrication, Supply and Installation of PSC Porcupine.
Lot 1 at a cost of 210 lakhs; Lot 2 at a cost of Rs. 230 lakhs
Lot 3 at a cost of Rs. 193 lakhs Lot 4 at a cost of Rs. 240.4 lakhs
(b) Due to delay in issue of the environmental clearance by the Ministry of Environment, Forest and Climate Change, Wild Life Division Kaziranga sub-project could not be taken up under Tranche-I. However, the same sub project has been included in Tranche-II. There was no delay in clearance of DPR from CWC as the same could not be processed at CWC for non-receipt of the environmental clearance from the Ministry of Environment, Forest and Climate Change Wild Life Division. Now, Kaziranga sub-project is proposed in Tranche-II, at a cost of Rs. 125.995 Cr and TAC clearance has been accorded by CWC in 130th TAC meeting held on 30.09.2016.
(c) There are no bottlenecks for implementation of Kaziranga sub-project at present, subject to extension of Multi Tranche Financing Facility (MFF) period by the Department of Economic Affair, (DEA) Govt. of India.
*****