Question : CONSTRUCTION OF SANCTIONED RAILWAY LINES



(a) whether the Railways have been implementing the project of construction of already sanctioned Railway lines in the State of Andhra Pradesh;

(b) if so, details thereof along with the status of Nadikudi- Srikalahasti new railway line;

(c) whether any funds have been allocated for the said rail line and if so, details thereof; and

(d) the time by which it is likely to be completed?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI MANOJ SINHA)

(a) to (c): Yes Madam. 16 new line projects and four doubling projects falling partly/ fully in the State of Andhra Pradesh have been taken up for execution. Further, nine more doubling projects have been included in the Railway Budget 2015-16 subject to obtaining of requisite clearances.

As regards Nadikudi - Srikalahasti New Line project, the same has been taken up at an anticipated cost of `1313 crore with proposed allocation of `110 crore for the year 2015-16. The State Government of Andhra Pradesh has agreed to provide land free of cost and to share 50% of construction cost. Land plans for 35 kms length have been submitted to State Government for acquisition.

(d): Time for completion cannot be fixed in the absence of availability of entire land.