MINISTER IN THE MINISTRY OF PETROLEUM & NATURAL GAS(SHRI MURLI DEORA)
(a) & (b): GAIL has, subject to certain conditions, decided to provide additional equity contribution of Rs.475 crores to Ratnagiri Gas and Power Private Limited (RGPPL) to be used for completion of the LNG terminal.
(c): Out of three power blocks, two power blocks are operational. The third power block is likely to become operational by February 2008. LNG terminal is expected to be completed without breakwater by December 2008; this terminal will become fully operational after completion of breakwater facilities in March 2011.