MINISTER OF THE STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (SHRI KAMAL NATH)
(a) to (e) A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (e) OF LOK SABHA STARRED QUESTION NO. 221 TO BE ANSWERED ON
10TH AUGUST, 2010 ASKED BY SHRI S. R. JEYADURAI AND SHRI ABDUL REHMAN REGARDING ROAD WIDENING PROJECTS.
(a) & (b) Yes Sir. One hundred and thirty seven projects implemented by National Highways Authority of India
(NHAI), and fifty projects implemented by various State Public Works Departments (PWDs) and Border Roads
Organization (BRO) have been delayed. State-wise details are annexed.
(c) to (e) The delays have occurred due to various reasons such as land acquisition, shifting of utilities,
obtaining environment, forest clearances and railway approvals, poor performance of contractors, law & order
problems in some States, etc. The targets for each individual projects have been reset and all the projects
are targeted for completion by 31st March 2012, except for terminated contracts.