MINISTER OF STATE IN THE MINISTRY OF SURFACE TRANSPORT
( DR. DEBENDRA PRADHAN )
(a): The loading and unloading rate at the ports is consistant with the available equipments and labour productivity. However, there is a scope for reducing the time taken for cargo handling by modernising the system of loading/unloading of the cargo at Ports.
(b): Demurrage is not payable by the shippers during the loading / unloading process irrespective of the time taken.
(c)&(d): The level of mechanisation, labour productivity and management practices in the international ports are different from those existing at Indian Ports. A direct comparison of delays in loading and unloading of cargo at Indian Ports with international Ports may be of relevance, as the type of ships that call at the international ports, handling methods, the equipment used and the type of cargo vary widely. To minimise the delays, the following measures are being taken :-
i) Mechanisation and modernisation of cargo handling equipments.
ii) Replacement of obsolete equipment.
iii) Rationalisation of manning scales.
iv) Privatisation in different areas in Port sector.
v) Streamlining of procedure and change in cargo handling methods.
vi) Introduction of Electronic Data Interchange.