MINISTER OF STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS
AND MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI O. RAJAGOPAL )
(a) to (c) : A Statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF
UNSTARRED QUESTION NO. 1868 BY DR. ASHOK PATEL TO BE
ANSWERED IN LOK SABHA ON 14.03.2002 REGARDING EXPANSION OF
STATIONS
(a) to (c) : Expansion of facilities at New Delhi and Hazrat Nizamuddin are sanctioned works. Additional
terminal facilities are being constructed at these
stations. The latest anticipated costs of the important
works, outlays expected to end of 2001-02 and outlay
proposed for 2002-03 are given below:-
S. Name of the Latest Outlay Outlay Status
No. Work Anticip Expected Proposed ated to for Cost the end 2002-03 of 2001- 02
(Rupees in Crores)
1. New Delhi : 16.09 15.09 1.00 The work is
Development of in advanced
Station â Phase- state of
III progress.
2. New Delhi : 26.08 11.55 7.36 The work is
Development of in progress.
Station â Phase-
IV
3. Hazrat 15.69 2.76 2.50 The work is
Nizamuddin : in progress.
Additions and
alternations in
Coaching Yard
4. New Delhi - 50.00 0.77 1.00 The work is
Station in progress.
building
5. Delhi & Hazrat 1.04 0.01 0.40 The work is
Nizamuddin â in progress.
Upgradation of
passenger
amenities in
connection with
model station
Any additional facility needed will be considered as and
when required.