MINISTER OF STATE IN THE MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION, PLANNING, SPACE, ATOMIC ENERGY & COMMERCE AND INDUSTRY (SHRI S.B. MOOKHERJEE)
(a) Yes, Sir.
(b) The norms for approval of new large social and infrastructure
projects as notified by Ministry of Finance as per the O.M.
No. 1 (3) PF II/2001, dated 18.2.2002 are as follows:
Project / Scheme Outlay Approval Authority
Less than Rs.50 crores Minister in-charge of Administrative Ministry
Rs.50 crores and above but Minister of Administrative
less than Rs. 100 crores Ministry and the Finance Minister
Rs.100 crores and above Cabinet / CCEA
Proposals for new autonomous Cabinet / CCEA
organisations irrespective of
outlay
(c) Yes, Sir.
(d) The time frame for the appraisal of projects has been reduced
from 24 weeks to 16 weeks as per the New Guidelines issued by
the Department of Expenditure as per the O.M. No. 1 (2)-PF
II/03, dated 7th May, 2003