THE MINISTER OF STATE FOR SCIENCE & TECHNOLOGY AND EARTH SCIENCES (INDEPENDENT CHARGE), PMO,PERSONNEL, PUBLIC GRIEVANCES AND PENSIONS AND PARLIAMENTARY AFFAIRS.
(SHRI PRITHVIRAJ CHAVAN):
(a) The generation of nuclear energy in the X Plan was 90,354 Million Units (MUs) as
compared to a target of 82,495 MUs. The target for the XI Plan was 1,63,395 MUs, which was
revised to 1,24,608 MUs at Mid-Term-Appraisal (MTA) stage. The generation in the first three
years of the XI Plan has been 50,714 MUs and the expected generation in full plan period is
about 1,06,000 MUs.
(b) The targets were fixed on the assumption of availability of imported uranium for
reactors under safeguards. Accessing the imported uranium through international cooperation
has taken longer time. In addition there has been delay in augmentation of uranium supply from
indigenous sources.
(c) The indigenous fuel supply is now improving progressively. Full requirement for
unsafeguarded reactors will be met on operation of the new uranium mine and mill in
Tummalapalle in Andhra Pradesh in the year 2012. With the availability of imported uranium
for the safeguarded reactors and of indigenous uranium for the unsafeguarded reactors, it
is expected that nuclear power plants will operate at high plant load factors during the next
five year plan.