MINISTER OF STATE FOR ROAD TRANSPORT AND HIGHWAYS (INDEPENDENT CHARGE) (MAJOR GENERAL (RETD.) B.C. KHANDURI, AVSM)
(a) The targets laid for development scheme in respect of Uttar Pradesh were fully achieved. As regards the State of Jharkhand, which was created on 15.11.2000, the targets were substantially achieved.
(b) Details given in Annex-I.
(c) Do not arise in the case of Uttar Pradesh. Minor shortfall of 5% in the case of Jharkhand is attributed due to delay in the award of work as a result of its separation from the State of Bihar.
ANNEX-I
STATEMENT REFERRED TO IN REPLY TO PART (b) OF THE LOK SABHA UNSTAREED QUESTION NO 4326 FOR ANSWER ON 16.4.2001 ASKED BY SHRIMATI RAJKUMARI RATNA SINGH AND PROF. DUKHA BHAGAT REGARDING DEVELOPMENT SCHEME OF NATIONAL HIGHWAYS.
Targets and achievements during the last three years pertaining to the State of Uttar Pradesh and Jharkhand are indicated as under:-
Items Year 1998-99 Year 1999-2000 Year 2000-2001 Targets Achievements Targets Achievements Targets Achiev
Uttar Pradesh
1. Number of works. 50 53 50 50 50 51
2. Strengthening weak 85 85 60 80 80 80 two lane Pavement (Km)
3. Improvement of riding - - 185 185 197 197 quality works (Km) (IRQP)
Jharkhand
1. Strengthening weak two - - - - 15 14 lane Pavement (km)
2. Improvement of riding - - - - 40 37.80 quality works (Km).(IRQP)