Question : SURVEY FOR NEW RAIL LINE



(a) whether the Railways have conducted any survey for laying of new railway lines in the State of Gujarat;

(b) if so, the details thereof during the last three years and the current year; and

(c) the steps taken by the Railways in this regard?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI MANOJ SINHA)

(a): A Statement is laid on the Table of the House.

STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 4668 BY SHRI DEVAJIBHAI G. FATEPARA TO BE ANSWERED IN LOK SABHA ON 22.12.2014 REGARDING SURVEY FOR NEW RAIL LINE.

(a) to (c): During the last 3 years and current year, following surveys for new line projects falling fully/ partly in the State of Gujarat have been completed.

 S.	Name of	Length	Cost No.	the project	in Km.	(`in crore) 1	Porbandar-Saradiya-	104	416	Junagarh 2	Bhavnagar-Mahuva-	268	1080	Pipavav-Una-Kodinar 3	Bhavnagar-Khambhat	131	737	via Mitli 4	Dholera-Bhimnath	28	253 5	Jaisalmer-Kandla	194	786	(i.e. Barmer-Bhabhar) 6	Tharad-Vav to Suigam	81	371	border (Dhenera-	Tharad-Vav-Suigam) 7	Veraval-Porbandar	133	1232 8	Botad-Gondal via	108	1058	Jasdan new line 
Out of the above, Shapur-Siradiya (46 km) which is a part of Porbandar-Saradiya-Junagarh survey, has been sanctioned at a cost of ` 196 crore Remaining projects could not be sanctioned due to their un-remunerative nature, huge throw- forward of ongoing projects and limited availability of funds.