THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
At present, 2/4/6-laning, strengthening, improvement etc. works in the length of about 3,200 km have been started during the last 4 years and the current year in the State of Karnataka, out of which, length of about 2,000 km have been completed. Length of 117 km out of 120 km and 46.50 km out of 72.70 km has been completed in development/ upgradation to four-lane of Hospet –Chitradurga section of NH-50 (Old NH-13) and six-lane of Chitradurga – Davanagere Section of NH-48 (Old NH-4) projects respectively.
*****
Download PDF Files