THE MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)
(a): Zone-wise length of railway liens converted since Project Unigague was launched on 01.04.1992 are as under:
Zone Length (in Kms)
Central Railway 150 Eastern Railway Nil Northern railway 1572 North Eastern Railway 964 Northeast Frontier railway 836 Southern Railway 2346 South Central Railway 1539 South Eastern Railway 278 Western Railway 1104
Total 8789
(b) to (d): The details of progress made regarding on-going
gauge conversion works, expenditure incurred thereon, cost
of the project and funds allocated during the last three
years are given in the enclosed statement.
Statement
Ongoing gauge Conversion works ( Rs. In Crs.)
Zone Project Cost Out- Out- Expe- Out- Remarks lay lay cted lay 99- 2000- exp. 2001-02 2000 01 up to Mar. 2001
CR Miraj-Latur 329 46.5 15.00 105.3 20 The work is being progressed in phases. In the first phase, gauge conversion work from kurduwadi to Pandharpur (52 km) has been completed. Residual works in the section are in progress. On Latur road-latur (42 km) earthwork and major and minor bridges have been completed. Ballast and collection is nearing completion. Work on Kurduwadi-Latur (143 km) has been taken up between kurduwadi and Yedshi (113 km) section. 29 out of 173 minor bridges and 5 out of 8 major bridges have been. No work on Osmanabad diversion (30 km) has been taken up. Miraj-Pandharpur (137 km) ph.IV work will be taken up as last phase of the project.
NER Gonda-Bahraich- 48 01.00 0.10 0 1 The work will be taken up Sitapur-Lucknow after the necessary clearances Ph.I## have been obtained. Samastipur- 70 01.00 0.10 0 5 The work will be taken up Khagaria## after the necessary clearances have been obtained. Jayanagar- 335.77 10 8.00 8.55 10 Jayanagar-Dharbhanga is Darbhanga- to be done in first phase. Narkatiaganj Work is in progress. Earthwork for 32 km completed. Tenders for earthwork and ballast supply have been finalized. For Ph.II work from Darbhanga to Narkatiaganj. Tenders for earthwork are under finalization. Recently material modfication for gague conversion of Narkatiaganj- Bhikanatori branch line has been sanctioned as a part of this project. Railway asked to submit material modification estimate accordingly. Mansi-Saharsa 89.49 10 3.00 23.51 3 Work is in progress. incl. MM for Earthwork has been completed extension upto in 29.17 km. 9 out of 13 Dauram-Madhepur minor bridges completed. 1 major bridge out of 10 completed. 2 bridges on Bagmati river are in progress. Tender for 2 major bridges on river Kosi (Br. No.44, 45) are under finalization. Open line is constructing 2 important bridges. Completion of these bridges would take 2-3 years period. Work of extension from Saharsa to Dauram Madhepur GC (21 km) included in the Budget 2001-02 as a Material Modification. The work would be completed in the coming years as per availability of resources. Hajipur-Bachwara 75.56 1 3.00 74.33 0.1 Work completed and commissioned. Shortfall in ballast is being made good. Work of LWR has been completed. Mathura-Achnera 33.67 01.00 1.00 0.1 2 It is planned to do this work alongwith Kanpur-Kasganj-Mathura. Khadda-Gorakhpur 102.49 2.5 1.00 93.49 9 The work has been completed. Residual work of increasing ballast cushion and LWR conversion is expected to be completed shortly. Kanpur-Kasganj- 609.04 26 26.00 52.44 26 Work is planned to be Mathura-Bareilly completed in 4 phases. Phase-I: incl. MM for Kanpur Farukhabad (140 km). extension from Earthwork is nearing completion Bareilly to and 103 out of 169 minor bridges Lalkuan have been completed. Work is in progress in 2 out of 5 major bridges. Ph.II Farukhabad-Kasganj (108 km). Earthwork and bridges have been taken up. Ph.III Kasganj-Mathura (105 km): No work has been taken up in this stretch so far. Ph.IV Kasganj-Bareilly (107 km): Earthwork and bridges are in progress. Gonda-Gorakhpur 250 01.00 0.10 0 1 The work would be taken up Loop with Anand after the requisite clearances nagar Nautwnwa## have been obtained. Indara-Phephana 35 1 0.10 34.48 0.1 The work has been completed and commissioned. Narkatiaganj- 67.87 1.5 3.00 61.88 5 The work has been completed Valmikinagar and commissioned. Residual work of increasing ballast cushion and LWR conversion is expected to be completed shortly. Samastipur- 41.54 - 0.10 37.88 0.1 Work completed and commissioned. Darbhanga Kashipur-Lalkuan 58.89 20 9.98 55.43 2 The work has been completed and commissioned. Chhapra-Aunrihar 170.93 1 0.10 169.91 0.1 Work completed and commissioned. Muzaffarpur- 121.86 4 2.00 121.76 0.1 The work has been completed Raxaul Raxaul- and commissioned. Birganj) The work for Birganj to Raxaul (5 km) which is sanctioned as a material modification has also been completed. Kaptanganj-Thave- 268 01.00 0.10 0 1.1 The work will be taken up Sivan-Chhapra## after necessary clearances have been obtained. Katihar-Jogbani 257 0.00 10.00 10 15 The work will be taken up (including after the requisite clearances Katihar- have been obtained. The Radhikapur)## gauge conversion of Katihar- Radhikapur will be taken up as a material modification to main work. Lumding-Silchar 696 40. 40.00 69.77 40 Final location survey with MM to completed except some extension from geotechnical investigation Badarpur to which are in progress. Bhariagram Preparation of land acquisition plan and papers has been taken up. RITES have already completed the paper alignment for entire length and staking of the alignment has been completed in 150 km. Earthwork and bridges are now in progress between Lumding and Silchar in 90 km length (40 km from Lumding end and 50 km from Silchar end). 40% for the earthwork in this 90 km length has been completed, and 60 minor bridges out of 138 in this length have also been completed. Work of Silchar-Jiribam gauge conversion is being carried out as a material modification of this work. Work of gauge conversion of Badarpur to Baraigram (44 km) included in the Budget 2001-02 as a Material modification. New Guwahati- 194.1 0.00 01.20 192.49 1.61 Work has been Lumding completed and commissioned. Katakhal-Bairabh 200 2 0.10 0.1 5 Requisite clearances have since been received. Preliminary arrangements are being made for starting the work. New Jalpaiguri- 535.88 69 80.00 128.74 80 The work is in very good Siliguri-New progress and is being Bongaigaon accorded high priority. It is planned to be completed by Dec.2003 subject to availability of resources. Lumding-Dibrugarh 738.54 2 10.00 687.34 2 The work of main line from with linked Lumding to Dibrugarh. fingers @ Tinsukhia-Lekhapani and branch lines from Furkating to Mariani and Simalguri- Moranhat has been completed. Gauge Conversion work on Amguri- Tuli and Makrum-Dangari is in progress and will be completed in 2001-02.
NR Bhildi-Samdri 244.92 5 5.50 3.69 4.5 This work was sanctioned in 1990-91 as a part of Kandla- Bhatinda rail link. The work have been recently defrozen. Funds have been allotted. Preliminary, arrangements are being made to take up the work. Luni-Barmer- 283.94 30 25.00 42.14 25.4 Earthwork between Luni-Samdari Munabao @ (50 km) has been completed and is in progress between Samdari and Barmer. 61 minor bridges out of 104 have also been completed and 4 out of 9 major bridges also completed. Ballast collection is in progress. 2.1 lakh cum out of 6.25 lakh cum ballast has been received. It is proposed to take up work inphases from Luni to Samdari, Samdari to Jasai and then Jasai onward. The work will be completed in the next 3 years as per availability or resources. Luni-Marwar & 118.77 2 0.10 111.76 0.6 The work has been completed Jodhpur-Luni Financial adjustments are being made. The residual work of block proving with axle counters is in progress and will be completed in 2001-02. Sriganganagar- 68.71 01.00 0.10 0.08 0.1 The work will be taken up Sarupsar## after the necessary clearances have been obtained. Rewari-Sadulpur## 282.76 01.00 0.10 0.01 2 The work will be taken up including MM after the necessary from Sadulpur- clearances have been Hissar obtained. New work from Sadulpur to Hissar GC included in the Budget 2001-02 as a Material modification. Phulera-Jodhpur- 21.46 1 0.10 0 0.01 The work from Phulera- Pipar Road-Bilara Jodhpur has been completed and commissioned. The rest of section from Pipar Road to Bilara has been sanctioned as a material Modification. Due to low operational priority and very light traffic on Pipar Road- Bilara section, work is temporarily pended and will be progressed as per availability of resources.
SCR Guntur-Guntakal 516.09 10 10.59 440.05 20 Guntur to Guntakal completed. and Guntakal- In Guntakal-Kalluru Kalluru @ New modification to alignment line from and gradients are being Pendakallu of worked out. Now with the Gooty sanction of Dharmavaram- Pakala, for which CCEA clearance is yet to be obtained, gauge conversion at Guntakal-Pakala would be done in one phase. Work is in good progress on new line portion from Pendekallu-Gooty and work will be completed in 2001-02, subject to availability of resources. Secunderabad- 287.83 20 20.00 35 19.87 The work has been taken up Mudkhed & in first phase from Mudkhed- Jankampet-Bodhan Nizamabad (96 km). Supply of ballast 1,50,650 cum out of 2,34,000 cum has been collected at site. On Mudkhed-Nizamabad section, earthwork in seven reaches has been completed and in balance 13 reaches works are in progress. Work has also been taken up in the remaining sections. The possibility of getting private funding for part of the work is being explored, with a view to expedite its completion. Mudkhed-Adilabad 170.51 1 2.00 37.6 20 The work has been taken up under BOLT scheme. Agency has not been able to progress the work due to financing problems. Agency has tied up with M/s HUDCO for financing. In case finances are made available project is expected to be completed in 18 months time. Solapur-Gadag 263.91 7 10.00 130.04 10 The work is being done in phases. The work on Solapur-Hotgi and Hotgi to Bijapur has been completed. Work is in progress on rest of fosection form Bijapur to Gadag which will be completed in the coming years as per availability of resources. Funding through KRIDES is being tried with a view to expedite early completion of this work. Katpadi-Pakala- 173.5 20 12.00 41.69 20 Out of 19 major bridges, Tirupati 15 have been completed and 4 are in progress. Earthwork and ballast supply is also in progress (60%) in the entire section. Work is proceeding well and will be completed in the coming years as per availability of resources. Akola-Purna 228 - 10.00 10 10 Final Location Survey is in progress. Arrangements are being made to take up earthwork and bridges in first section from Purna to Hingoli (95 km). Secunderabad- 351.05 5 5.00 334.45 0.55 The work has been completed. Dronachellam Dharmavaram- 251.22 10.00 0.10 0.1 1 The work would be taken up Pakala## after the requisite clearances have been obtained. Gondia-Chandafort 242.82 6 1.26 242.32 0.1 The work has been completed. Financial adjustments are being made. Naupada-Gunupur## 66.35 100.00 5.10 5.14 0.1 CCEA clearance not yet received. The work will be taken up after the necessary clearances have been obtained. Rupsa-Bangariposi 80 14 1.00 9.64 4 Earthwork and bridges are in progress on the entire length. Work upto cess level has been completed in the first two sections from km 0 to 51 km. Rest of section is in progress. Precast box segments for minor bridges from Rupsa to Baripada (51 km) has been completed. Ranchi-Lohardaga 185.31 10 3.00 15.97 4 The earthwork and minor with extension bridges have been taken up to Tori on the Phase-I Ranchi-Lohardaga section. Work of 14 arch bridges & casting RCC Box is in progress. Tenders have been awarded for one major bridge and are being called for the remaining 3 major bridges.Tori- Lohardaga (New Line):- Final Location Survey has been completed. Bankura-Damodar 266.23 5 40.00 40.45 50 Tenders for earthwork and River Project minor bridges have been including MM for finalized from km 0.6 to 57.1 extension of New and have been invited for line from the rest of the section. Bowaichandi to Extension of new line work Khanna from Bowaichandi to Khana (22 km) included in the Budget 2001-02 as a Material Modification. Jabalpur-Gondia 386.3 22 16.80 16.02 15 Final Location survey from including Gondia to Balaghat including Balaghat- Balaghat-Katangi Katangi has been completed including geo-technical investigations of major bridges. The survey between Balaghat-Jabalpur is in progress. Land has been acquired upto Balaghat Formation work, bridge work and ballast supply are in progress between Gondia and Balaghat.
SR Dindigul-Trichy 131.07 9 5.50 95.85 0.5 The work has been completed and commissioned. Trichy-Manmadurai 175 - 7.00 4 10 New work included in the Budget 2000-01. Detailed planning has been taken up. Cuddalore-Salem 198.68 0.00 1.00 1 6 The work would be taken up via after obtaining the Vriddhachalam## @ requisite clearances. Yelahanka- 57.54 2 0.10 57.44 0.1 The work sanctioned has been Chickballur and completed and commissioned. Kolar-Bangarpet Yashwantpur-Salem 176.29 2.99 0.10 175.34 0.5 Work has been completed. Section from Banyapannahalli to Salem has been commissioned. However, Banyapannahall- Yasshwantpur is not getting commission due to public agitation to get ROB at Hebbal and Lingraypuram. State Govt. is being approached for its early commissioning. Thanjavur- 331 10 10.00 6.03 10 The work would be taken up Villupuram main after line ## obtaining requisite clearances. Madurai- 240 5 5.00 5.39 10 Necessary clearances Rameshwaram have been obtained. Earthwork and bridges have been taken up. No target date has yet been fixed. Villupuram- 30 005.00 10.00 9 5 The necessary clearances Pondicherry have been obtained. Preliminary arrangements are being made for starting the work. Trichchirappali- 146.11 2 3.00 81.23 13 The section from Trichy to Nagore-Karaikal Thanjavur (50 km) has been completed and commissioned. Work on rest of the section is in progress. No target date has been fixed. Nagpattinam-Vallankani has been sanctioned as a material modification to this work but alignment is under modification is consultation with the State Govt. Chennai Beach- 696.83 67.5 35.50 409.52 0.5 Work has been compelted and Tiruchchirappali commissioned. However, 12 and crossing stations remain to be Arakonnam_Chengal provided of which 5 will pattu be completed in 2000-01 and th rest in 2001-02. Villupuram- 175 - 5.00 2.23 5 FLS is in progress. Katpadi Detailed planning has been taken up. Quilon- 327.61 10 15.00 21.97 20 In Virudhnagar-Tenkasi and Tirunelveli- Tirunelveli-Tiruchendur, Trichendur & bridge work and earthwork Tenkasi- has been taken up. Final Virudhnagar location survey has been taken up in the ghat section between Punalpur and Tenkasi to ease gradient and curves to suit BG. The work is being progressed as per availability of resources. Mysore- 175 10.00 0.10 0.01 1 This work will be taken up Chamarajnagar## after the necessary clearances have been obtained. Mysore-Hassan 193.99 10 10.00 184.39 0.5 The work has been completed except on Lakshman Tirtha bridge, which is being built on a diversion. The bridge will be completed by March, 2001. Arsikere-Hassan- 325.98 28 26.00 136.38 58.1 Arsikere-Hassan- Mangalore Sakleshpur has been completed & commissioned. Earthwork bridges, ballast collection on the rest of the section are in progress. Formation is ready between Mangalore and Kabakaputtur (44 km) and Kabakaputtur to Subramanya road will be completed this year. Lowering of tunnels and widening of bank in ghat section has been taken up together with geonet treatment to prevent slip and slope failure in ghat section. The work will be completed in the coming years as per availability of resources. Funding through KRDC is being tried to expedite the completion of the work. Bangalore-Hubli- 427.7 3 2.00 397.66 0.5 The work on the line from Birur-Shimoga Bangalore-Hubli & between Birur & Shimoga has been completed. Work is in progress on Shimoga_Talguppa. Earthwork has been taken up from Shimoga-Kamsi (25 km) and Sagara-Talguppa (15 km) where progress is 90%. This section has light traffic and work is being progressed as per availability of resources.
WR Phulera-Marwar- 632.38 39 15.00 618.85 13.5 Work has been completed and Ahmedabad@ commissioned. Residual works are in progress. Ajmer-Udaipur 294.69 25 10.00 19.18 15 The work is progressing Chittaurgarh between Udaipur and including MM for Chittaurgarh in first phase extn from Udaipur in first phase 4.57 lac cum to Umra of earthwork has been completed out of 17.41 lac cum, substructure of 86 minor bridges have been completed and other 12 bridges out of the total 202 minor bridges is in progress. Out of total of 8 major bridges, one has been completed in all respect and substructure of 4 more bridges have been completed. No target date has yet been fixed. New work from Udaipur to Umra (11 km) included in the Budget 2001-02 as a Material modification. Agra-Bandikui 178.03 10 9.09 20.6 10 Earthwork and bridges are in progress. 60 minor bridges out of 193 nos, substructure of 4 major bridges out of 9 nos. and 8 minor bridges have been completed an 1.3 lacs cum earthwork out of 3.07 lac cum has been completed. The work is being progressed as per availability of resources. Bhildi( Mehsana- 134.75 7 6.90 15.4 15 Mehsana-Patan MG section has Patan)-Viramgam @ been restored. Tenders for Earthwork, minor & major bridges have been awarded. Substructure of all 3 major bridges and all 77 minor bridges have been completed. 78000 out of 1.12 lakh cum earthwork has also been completed. The target for completion of this work has not yet been fixed. Work on new line for Patan- Bhildi is frozen. Dharangadhara- 10.17 1 0.01 0.01 2 This work is being done on Kuda siding 1/3 cost sharing basis with co-sharers are Ministry of Railways. Gujarat Government and the Ministry of Industry. Earthwork has been completed and full ballast supply has been taken. Second hand Rails are being arranged from CR. The co-sharers have deposited their full shares. Work is expected to be completed during 2001-02. Surendernagar- 441.63 30 40.00 46.66 34.4 The work is in good progress. Bhavnagar-Rajula- 57 major bridges out of Mahuwa with the total 59 major extn. Upto bridges and 264 minor Pipavav of Sihor- bridges out of 280 minor Palitana @ bridges is in progress. Out of total 25.11 lac cum of earthwork, contracts for 9.37 lac cum of earthwork have been awarded. Substructures of 185 minor, 54 major and 6.27 lac cum of earthwork has been completed. Papers for Land Acquisitions for New line potion from Rajula city to Pipavav have been submitted to State Govt. The formation and bridge work are in good progress. Track, signaling work etc. are to be done by an SPV consisting of Ministry of Railways and GPPL. NOU has been signed. Further follow up action is being taken. Target date is Dec.2002. Surender Nagar-Dharangadhara GC has been sanctioned as a material modification. Wankaner-Maliya 100.85 35 30 88.42 5.5 The work is in good progress. Miyana The first phase from Maliya Mayana to Navlakhi via Dahinsara has been completed and opened for traffic on 30.09.1999. Mega block for the project has started. Track linking has been completed. Work on the rest of section is targeted for completion during 2001-02. Gandhidham-Bhuj 50.75 20 20.00 43.32 1 The work has been completed. Rajkot-Veraval 291.61 3 10.00 25.58 20 Earthwork minor bridges and including MM strengthening of major bridges for extension have been taken up and are in from Wansjalia progress. 2.82 lacs cum to Jetalsar earthwork out of 4.71 lacs cum, substructure of 27 major bridges out of 32 major bridges, 136 minor bridges out of total 156 nos. and 1.38 lacs cum of Ballast, out of 3.94 lacs cum have been completed. Contracts for superstructure of all Bridges has been awarded and is in progress. The work is expected to be completed during the coming years as per availability of resources. New work from Jetalser to Wansjaliya (90km) included in the Budget 2001-02 as a Material Modification. Gandhidham- 370.74 10 3.00 0.05 15 Necessary clearances have been Palanpur obtained. Preparation of plans and estimate has been taken up.