Question : GAUGE CONVERSION



(a) the total length of railway lines converted so far, zone-wise;

(b) the details of progress made so far regarding completion of on-going gauge conversion of railway lines subject-wise;

(c) the expenditure incurred thereon so far alongwith estimated cost thereof, project-wise; and

(d) the funds allocated to each project during 1999-2000, 2000-2001 and 2001-2002 ?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)

(a): Zone-wise length of railway liens converted since Project Unigague was launched on 01.04.1992 are as under:

Zone	Length (in Kms)
Central Railway 150 Eastern Railway Nil Northern railway 1572 North Eastern Railway 964 Northeast Frontier railway 836 Southern Railway 2346 South Central Railway 1539 South Eastern Railway 278 Western Railway 1104
Total 8789



(b) to (d): The details of progress made regarding on-going gauge conversion works, expenditure incurred thereon, cost of the project and funds allocated during the last three years are given in the enclosed statement.

Statement
Ongoing gauge Conversion works	( Rs. In Crs.)
Zone	Project	Cost	Out- Out- Expe- Out-	Remarks	lay lay cted lay	99- 2000- exp. 2001-02	2000 01 up to Mar. 2001
CR	Miraj-Latur	329 46.5 15.00 105.3 20	The work is being progressed in phases. In the first phase, gauge	conversion work from kurduwadi to Pandharpur (52 km) has been completed. Residual works in the section are in progress. On Latur road-latur (42 km) earthwork and major and minor bridges have been completed. Ballast and collection is nearing completion. Work on Kurduwadi-Latur (143 km) has been taken up between kurduwadi and Yedshi (113 km) section. 29 out of 173 minor bridges and 5 out of 8 major bridges have been. No work on Osmanabad diversion (30 km) has been taken up. Miraj-Pandharpur (137 km) ph.IV work will be taken up as last phase of the project.
NER	Gonda-Bahraich-	48 01.00 0.10 0 1 The work will be taken up	Sitapur-Lucknow after the necessary clearances	Ph.I## have been obtained.	Samastipur-	70 01.00 0.10 0 5	The work will be taken up	Khagaria## after the necessary clearances have been obtained.	Jayanagar-	335.77 10 8.00 8.55 10	Jayanagar-Dharbhanga is	Darbhanga- to be done in first phase.	Narkatiaganj	Work is in progress. Earthwork for 32 km completed. Tenders for earthwork and ballast	supply have been finalized. For Ph.II work from Darbhanga to Narkatiaganj. Tenders for earthwork are under finalization. Recently material modfication for gague conversion of Narkatiaganj- Bhikanatori branch	line has been sanctioned as a part of this project. Railway asked to submit material modification estimate accordingly.	Mansi-Saharsa	89.49 10 3.00 23.51 3	Work is in progress.	incl. MM for	Earthwork has been completed	extension upto in 29.17 km. 9 out of 13	Dauram-Madhepur minor bridges completed. 1	major bridge out of 10 completed. 2 bridges on Bagmati river are in progress. Tender for 2 major bridges on river Kosi (Br. No.44, 45) are under finalization. Open line is constructing 2 important bridges. Completion of these bridges would take 2-3 years period. Work of extension from Saharsa	to Dauram Madhepur GC (21 km) included in the Budget 2001-02 as a Material Modification. The work would be completed in the coming years as per availability of resources.	Hajipur-Bachwara 75.56 1 3.00 74.33 0.1	Work completed and commissioned. Shortfall in ballast is being made good. Work of LWR has been completed.	Mathura-Achnera	33.67 01.00 1.00 0.1 2 It is planned to do this work	alongwith Kanpur-Kasganj-Mathura.	Khadda-Gorakhpur 102.49 2.5 1.00 93.49 9	The work has been completed. Residual work of increasing ballast cushion and LWR conversion is expected to be completed shortly.	Kanpur-Kasganj-	609.04 26 26.00 52.44 26 Work is planned to be	Mathura-Bareilly	completed in 4 phases. Phase-I:	incl. MM for	Kanpur Farukhabad (140 km).	extension from	Earthwork is nearing completion	Bareilly to	and 103 out of 169 minor bridges	Lalkuan	have been completed. Work is in progress in 2 out of 5 major bridges. Ph.II Farukhabad-Kasganj (108 km). Earthwork and bridges have been taken up. Ph.III Kasganj-Mathura (105 km): No work has been taken up in this stretch so far. Ph.IV Kasganj-Bareilly (107 km): Earthwork and bridges are in progress.	Gonda-Gorakhpur	250 01.00 0.10 0 1	The work would be taken up	Loop with Anand	after the requisite clearances	nagar Nautwnwa##	have been obtained.	Indara-Phephana	35 1 0.10 34.48 0.1 The work has been completed and commissioned.	Narkatiaganj-	67.87 1.5 3.00 61.88 5 The work has been completed	Valmikinagar	and commissioned. Residual work of increasing ballast cushion and LWR conversion is expected to be completed shortly.	Samastipur-	41.54 - 0.10 37.88 0.1 Work completed and commissioned.	Darbhanga	Kashipur-Lalkuan 58.89 20 9.98 55.43 2	The work has been completed	and commissioned.	Chhapra-Aunrihar 170.93 1 0.10 169.91 0.1	Work completed and commissioned.	Muzaffarpur-	121.86 4 2.00 121.76 0.1	The work has been completed	Raxaul Raxaul-	and commissioned.	Birganj)	The work for Birganj to Raxaul (5 km) which is sanctioned as a material modification has also been completed.	Kaptanganj-Thave- 268 01.00 0.10 0 1.1	The work will be taken up	Sivan-Chhapra## after necessary clearances have been obtained.	Katihar-Jogbani 257 0.00 10.00 10 15	The work will be taken up	(including	after the requisite clearances	Katihar-	have been obtained. The	Radhikapur)##	gauge conversion of Katihar- Radhikapur will be taken up as a material modification to main work.	Lumding-Silchar	696 40. 40.00 69.77 40 Final location survey	with MM to	completed except some	extension from	geotechnical investigation	Badarpur to	which are in progress.	Bhariagram	Preparation of land acquisition	plan and papers has been taken up. RITES have already completed the paper alignment for entire length and staking of the alignment has been completed in 150 km. Earthwork and bridges are now in progress between Lumding and Silchar in 90 km length (40 km	from Lumding end and 50 km from Silchar end). 40% for the earthwork in this 90 km length has been completed, and 60 minor bridges out of 138 in this length have also been completed. Work of Silchar-Jiribam gauge conversion is being carried out as a material modification of this work. Work of gauge conversion of Badarpur to Baraigram (44 km) included in the Budget 2001-02 as a Material modification.	New Guwahati-	194.1 0.00 01.20 192.49 1.61	Work has been	Lumding	completed and commissioned.	Katakhal-Bairabh 200 2 0.10 0.1 5	Requisite clearances have since been received. Preliminary arrangements are being made for starting the work.	New Jalpaiguri-	535.88 69 80.00 128.74 80	The work is in very good	Siliguri-New	progress and is being	Bongaigaon	accorded high priority. It is planned to be completed by Dec.2003 subject to availability of resources.	Lumding-Dibrugarh 738.54 2 10.00 687.34 2	The work of main line from	with linked	Lumding to Dibrugarh.	fingers @	Tinsukhia-Lekhapani and branch lines from Furkating to Mariani and Simalguri- Moranhat has been completed. Gauge Conversion work on Amguri- Tuli and Makrum-Dangari is in progress and will be completed in 2001-02.
NR	Bhildi-Samdri	244.92 5 5.50 3.69 4.5 This work was sanctioned in 1990-91 as a part of Kandla- Bhatinda rail link. The work have been recently defrozen. Funds have been allotted. Preliminary, arrangements are	being made to take up the work.	Luni-Barmer-	283.94 30 25.00 42.14 25.4	Earthwork between Luni-Samdari	Munabao @	(50 km) has been completed and is in progress between Samdari and Barmer. 61 minor bridges out of 104 have also been completed and 4 out of 9 major bridges also completed. Ballast collection is in progress. 2.1 lakh cum out of 6.25 lakh	cum ballast has been received. It is proposed to take up work inphases from Luni to Samdari, Samdari to Jasai and then Jasai onward. The work will be completed in the next 3 years as per availability or resources.	Luni-Marwar & 118.77 2 0.10 111.76 0.6	The work has been completed	Jodhpur-Luni	Financial adjustments are being made. The residual work of block proving with axle	counters is in progress and	will be completed in 2001-02.	Sriganganagar-	68.71 01.00 0.10 0.08 0.1 The work will be taken up	Sarupsar##	after the necessary clearances have been obtained.	Rewari-Sadulpur## 282.76 01.00 0.10 0.01 2	The work will be taken up	including MM	after the necessary	from Sadulpur-	clearances have been	Hissar	obtained. New work from Sadulpur to Hissar GC included in the Budget 2001-02 as a Material modification.	Phulera-Jodhpur- 21.46 1 0.10 0 0.01	The work from Phulera-	Pipar Road-Bilara	Jodhpur has been completed and commissioned. The rest of section from Pipar Road to Bilara has been sanctioned as a material Modification. Due to low operational priority and very light traffic on Pipar Road- Bilara section, work is temporarily pended and will be progressed as per availability of resources.
SCR	Guntur-Guntakal	516.09 10 10.59 440.05 20	Guntur to Guntakal completed.	and Guntakal-	In Guntakal-Kalluru	Kalluru @ New modification to alignment	line from	and gradients are being	Pendakallu of	worked out. Now with the	Gooty	sanction of Dharmavaram- Pakala, for which CCEA clearance is yet to be obtained, gauge conversion at Guntakal-Pakala would be done in one phase. Work is in good progress on new line portion from Pendekallu-Gooty and work will be completed in 2001-02, subject	to availability of resources.	Secunderabad-	287.83 20 20.00 35 19.87 The work has been taken up	Mudkhed &	in first phase from Mudkhed-	Jankampet-Bodhan	Nizamabad (96 km). Supply of ballast 1,50,650 cum out of 2,34,000 cum has been collected at site. On Mudkhed-Nizamabad section, earthwork in seven reaches has been completed and in balance 13 reaches works are in progress. Work has also been taken up in the remaining sections. The possibility of getting private funding for part of the work is being explored, with a view to expedite its completion.	Mudkhed-Adilabad 170.51 1 2.00 37.6 20	The work has been taken up under BOLT scheme. Agency has not been able to progress the work due to financing problems. Agency has tied up with M/s HUDCO for financing. In case finances are made available project is expected to be completed in 18 months time.	Solapur-Gadag	263.91 7 10.00 130.04 10	The work is being done in phases. The work on Solapur-Hotgi and Hotgi to Bijapur has been completed. Work is in progress on rest of fosection form Bijapur	to Gadag which will be completed in the coming years as per availability of resources. Funding through KRIDES is being tried with a view to expedite early completion of this work.	Katpadi-Pakala-	173.5 20 12.00 41.69 20	Out of 19 major bridges,	Tirupati	15 have been completed and 4 are in progress. Earthwork and ballast supply is also in progress (60%) in the entire section. Work is proceeding well and will be completed in the coming years as per availability of resources.	Akola-Purna	228 - 10.00 10 10 Final Location Survey is in progress. Arrangements are being made to take up earthwork and bridges in first section from Purna to Hingoli (95 km).	Secunderabad-	351.05 5 5.00 334.45 0.55 The work has been completed.	Dronachellam	Dharmavaram-	251.22 10.00 0.10 0.1 1	The work would be taken up	Pakala##	after the requisite clearances have been obtained.	Gondia-Chandafort 242.82 6 1.26 242.32 0.1	The work has been completed. Financial adjustments are	being made.	Naupada-Gunupur## 66.35 100.00 5.10 5.14 0.1	CCEA clearance not yet received. The work will be taken up after the necessary clearances have been obtained.	Rupsa-Bangariposi 80 14 1.00 9.64 4	Earthwork and bridges are in progress on the entire length. Work upto cess level has been completed in the first two sections from km 0 to 51 km. Rest of section is in progress. Precast box segments for minor bridges from Rupsa to Baripada (51 km) has been completed.	Ranchi-Lohardaga 185.31 10 3.00 15.97 4	The earthwork and minor	with extension	bridges have been taken up	to Tori	on the Phase-I Ranchi-Lohardaga section. Work of 14 arch bridges & casting RCC Box is in progress. Tenders have been awarded for one major bridge and are being called for the remaining 3 major bridges.Tori- Lohardaga (New Line):- Final Location Survey has been completed.	Bankura-Damodar	266.23 5 40.00 40.45 50	Tenders for earthwork and	River Project	minor bridges have been	including MM for	finalized from km 0.6 to 57.1	extension of New	and have been invited for	line from	the rest of the section.	Bowaichandi to Extension of new line work	Khanna	from Bowaichandi to Khana (22 km) included in the Budget 2001-02 as a Material Modification.	Jabalpur-Gondia	386.3 22 16.80 16.02 15	Final Location survey from	including	Gondia to Balaghat including Balaghat-	Balaghat-Katangi	Katangi has been completed including geo-technical investigations of major bridges. The survey between Balaghat-Jabalpur is in progress. Land has been acquired upto Balaghat Formation work, bridge work and ballast supply are in progress between Gondia and Balaghat.
SR	Dindigul-Trichy	131.07 9 5.50 95.85 0.5	The work has been completed	and commissioned.	Trichy-Manmadurai 175 - 7.00 4 10	New work included in the Budget 2000-01. Detailed	planning has been taken up.	Cuddalore-Salem	198.68 0.00 1.00 1 6	The work would be taken up	via	after obtaining the	Vriddhachalam## @	requisite clearances.	Yelahanka-	57.54 2 0.10 57.44 0.1 The work sanctioned has been	Chickballur and	completed and commissioned.	Kolar-Bangarpet	Yashwantpur-Salem 176.29 2.99 0.10 175.34 0.5	Work has been completed. Section from Banyapannahalli	to Salem has been commissioned. However, Banyapannahall-	Yasshwantpur is not getting commission due to public agitation to get ROB at Hebbal and Lingraypuram. State Govt. is being approached for its early commissioning.	Thanjavur-	331 10 10.00 6.03 10	The work would be taken up	Villupuram main	after	line ##	obtaining requisite clearances.	Madurai-	240 5 5.00 5.39 10 Necessary clearances	Rameshwaram have been obtained. Earthwork and bridges have been taken up. No target date has yet been fixed.	Villupuram-	30 005.00 10.00 9 5	The necessary clearances	Pondicherry	have been obtained. Preliminary arrangements are being made for starting the work.	Trichchirappali- 146.11 2 3.00 81.23 13	The section from Trichy to	Nagore-Karaikal	Thanjavur (50 km) has been completed and commissioned. Work on rest of the section is in progress. No target date has been fixed. Nagpattinam-Vallankani	has been sanctioned as a material modification to this work but alignment is under modification is	consultation with the State Govt.	Chennai Beach-	696.83 67.5 35.50 409.52 0.5	Work has been compelted and	Tiruchchirappali	commissioned. However, 12	and crossing stations remain to be	Arakonnam_Chengal	provided of which 5 will	pattu	be completed in 2000-01 and th rest in 2001-02.	Villupuram-	175 - 5.00 2.23 5 FLS is in progress.	Katpadi	Detailed planning has	been taken up.	Quilon-	327.61 10 15.00 21.97 20	In Virudhnagar-Tenkasi and	Tirunelveli-	Tirunelveli-Tiruchendur,	Trichendur &	bridge work and earthwork	Tenkasi-	has been taken up. Final	Virudhnagar	location survey has been taken up in the ghat section between Punalpur and Tenkasi to ease gradient and curves to suit BG. The work is being progressed as per availability of resources.	Mysore-	175 10.00 0.10 0.01 1	This work will be taken up	Chamarajnagar##	after the necessary clearances have been obtained.	Mysore-Hassan	193.99 10 10.00 184.39 0.5 The work has been completed except on Lakshman Tirtha bridge, which is being built on a diversion. The bridge will be completed by March, 2001.	Arsikere-Hassan- 325.98 28 26.00 136.38 58.1	Arsikere-Hassan-	Mangalore	Sakleshpur has been completed & commissioned. Earthwork bridges, ballast collection on the rest of the section are in progress. Formation is ready between Mangalore and Kabakaputtur (44 km) and Kabakaputtur to Subramanya road will be completed this year. Lowering of tunnels and widening of bank in ghat section has been taken up together with geonet treatment to prevent slip and slope failure in ghat section. The work will be completed in the coming years as per availability of resources. Funding through KRDC is being tried to expedite the completion of the work.	Bangalore-Hubli- 427.7 3 2.00 397.66 0.5	The work on the line from	Birur-Shimoga	Bangalore-Hubli & between Birur & Shimoga has been completed. Work is in progress on Shimoga_Talguppa. Earthwork has been taken up from Shimoga-Kamsi (25 km) and Sagara-Talguppa (15 km) where progress is 90%. This section has light traffic and work is being progressed as per availability of resources.
WR	Phulera-Marwar-	632.38 39 15.00 618.85 13.5 Work has been completed and	Ahmedabad@	commissioned. Residual works are in progress.	Ajmer-Udaipur	294.69 25 10.00 19.18 15	The work is progressing	Chittaurgarh	between Udaipur and	including MM for Chittaurgarh in first phase	extn from Udaipur	in first phase 4.57 lac cum	to Umra	of earthwork has been	completed out of 17.41 lac cum, substructure of 86 minor bridges have been completed and other 12 bridges out of the total 202 minor bridges is in progress. Out of total of 8 major bridges, one has been completed in all respect and substructure of 4 more bridges have been completed. No target date has yet been fixed. New work from Udaipur to Umra (11 km) included in the Budget 2001-02 as a Material modification.	Agra-Bandikui	178.03 10 9.09 20.6 10	Earthwork and bridges are in progress. 60 minor bridges out of 193 nos, substructure of 4 major bridges out of 9 nos. and 8 minor bridges have been completed an 1.3 lacs cum earthwork out of 3.07 lac cum has been completed. The work is being progressed as per availability of resources.	Bhildi( Mehsana- 134.75 7 6.90 15.4 15	Mehsana-Patan MG section has	Patan)-Viramgam @	been restored. Tenders for Earthwork, minor & major bridges have been awarded. Substructure of all 3 major bridges and all 77 minor bridges have been completed. 78000 out of 1.12 lakh cum earthwork has also been completed. The target for completion of this work has not yet been fixed. Work on new line for Patan- Bhildi is frozen.	Dharangadhara-	10.17 1 0.01 0.01 2	This work is being done on	Kuda siding	1/3 cost sharing basis with co-sharers are Ministry of Railways. Gujarat Government and the Ministry of Industry. Earthwork has been completed and full ballast supply has been taken. Second hand Rails are being arranged from CR. The co-sharers have deposited their full shares. Work is expected to be completed during 2001-02.	Surendernagar-	441.63 30 40.00 46.66 34.4 The work is in good progress.	Bhavnagar-Rajula-	57 major bridges out of	Mahuwa with the	total 59 major	extn. Upto	bridges and 264 minor	Pipavav of Sihor-	bridges out of 280 minor	Palitana @	bridges is in progress. Out of total 25.11 lac cum of earthwork, contracts for 9.37 lac cum of earthwork have been awarded. Substructures of 185 minor, 54 major and 6.27 lac cum of earthwork has been completed. Papers for Land Acquisitions for New line potion from Rajula city to Pipavav have been submitted to State Govt. The formation and bridge work are in good progress. Track, signaling work etc. are to be done by an SPV consisting of Ministry of Railways and GPPL. NOU has been signed. Further follow up action is being taken. Target date is Dec.2002.	Surender Nagar-Dharangadhara GC has been sanctioned as a material modification.	Wankaner-Maliya 100.85 35 30 88.42 5.5 The work is in good progress.	Miyana	The first phase from Maliya Mayana to Navlakhi via Dahinsara has been completed and opened for traffic on 30.09.1999. Mega block for the project has started. Track linking has been completed. Work on the rest of section is targeted for completion during 2001-02.	Gandhidham-Bhuj	50.75 20 20.00 43.32 1 The work has been completed.	Rajkot-Veraval	291.61 3 10.00 25.58 20	Earthwork minor bridges and	including MM	strengthening of major bridges	for extension	have been taken up and are in	from Wansjalia	progress. 2.82 lacs cum	to Jetalsar	earthwork out of 4.71 lacs cum, substructure of 27 major bridges out of 32 major bridges, 136 minor bridges out of total 156 nos. and 1.38 lacs cum of Ballast, out of 3.94 lacs cum have been completed. Contracts for superstructure of all Bridges has been awarded and is in progress. The work is expected to be completed during the coming years as per availability of resources. New work from Jetalser to Wansjaliya (90km) included in the Budget 2001-02 as a Material Modification.	Gandhidham-	370.74 10 3.00 0.05 15	Necessary clearances have been	Palanpur	obtained. Preparation of plans	and estimate has been taken up.