THE MINISTER OF STATE (IC) FOR YOUTH AFFAIRS & SPORTS AND MINISTER OF STATE FOR WATER RESOURCES, RIVER DEVELOPMENT AND GANGA REJUVENATION
(SHRI VIJAY GOEL)
(a) & (b) The various types of pollution abatement schemes taken up to clean Ganga are categorized into ‘entry level activities’; ‘medium term activities’; and ‘long term activities’. There are 273 projects under Namami Gange Programme and are under different stages of implementation. All the projects are planned for completion by 2020. The status of the projects as on 30th September 2016 is given under Annexure-1.
(c) No Madam
(d) The expenditure incurred during 2014-15 and 2016-17 (upto 10.11.2016) is Rs.3,585.90 crores.
(e) Pollution abatement schemes for rivers other than Ganga Basin is handled by the Ministry of Environment, Forest & Climate Change through its National River Conservation Directorate (NRCD) Programmes.
*****
ANNEXURE-1
Annexure referred in reply to part (a) & (b) of Lok Sabha Question No.412 answered on 17.11.2016
S.NO. Type of Activity Total No. of projects State No. of project Nature of the Project Approved Project cost (cr) Project status Tentative year of Completion
1 Entry Level Projects 112 ghats 37 crematoria Uttarakhand 29 Ghats 150.5 Approved 2017-18
23 Crematoria Approved 2017-18
Uttar Pradesh 47 Ghats 397.76 Approved 2017-18
38 Crematoria Approved 2017-18
Bihar 19 Ghats 101.22 Approved 2017-18
3 Crematoria Approved 2017-18
Jharkhand 6 Ghats 28.49 Approved 2017-18
2 Crematoria Approved 2017-18
West Bengal 11 Ghats 21 Approved 2016-17
6 Crematoria Approved 2016-17
10 trash skimmers Trash Skimmers 10 Trash Skimmers 46.93 Approved 2016-17
2 Creation /rehabiltation of STPs 62 sewerage projects Uttarakhand 20 sewerage projects 382.76 Approved 2017-18
Uttar Pradesh 14 2308.79 Approved 2017-18
Bihar 13 2155.62 Approved 2017-18
Jharkhand 1 146.59 Approved 2017-18
West Bengal 6 1352.51 Approved 2017-18
Haryana 2 217.87 Approved 2016-17
Delhi 6 1547.7 Approved 2018-19
3 Afforestation 5 afforestation projects Uttarakhand 1 Afforestation 15.92 Approved 2016-17
Uttar Pradesh 1 9.52 Approved 2016-17
Bihar 1 6.03 Approved 2016-17
Jharkhand 1 7.99 Approved 2016-17
West Bengal 1 11.16 Approved 2016-17
4 Biodiversity Centres 6 Biodiversity centres Biodiversity Conservation and Ganga Rejuvenation, Part-1 under the NamamiGangeProgramme -(Wildlife Instutute of India) 3 Biodiversity centres 7.69 Approved 2018-19
Biodiversity Conservation and Ganga Rejuvenation, Part-2 under the NamamiGangeProgramme -(Wildlife Instutute of India) 3 Biodiversity centres 17.14 Approved 2018-19
5 Rural Sanitation 1 project Rural Sanitation initiatives for Ganga Rejuvenation in Jharkhand- UNDP 1 The major components of the projects are : A) Improved Sanitation B) Sanitation Linked Livelihood Activites C) Capacity Building 127 Approved 2016-2018
6 Water Quality Monitoring 1 project Water Quality Monitoring system for River Ganga (EAP - World Bank) 1 Real time water quality monitoring through 113 monitoring stations, Bio-monitoring, Community monitoring of Ganga water quality. 94.45 Approved 2018-19
7 Industrial Pollution 1 project Pollution Inventorization, Assessment and Surveillance on Ganga river 1 Pollution Inventorization, Assessment and Surveillance. 38.57 Approved 2016-17
8 Conservation of Dolphins 1 project Educating Schools and Communities for conserving habitat of Ganga River Dolphin (EAP) 1 1.28 Approved 2016-17
9 River front development projects 2 projects Uttarakhand 1 Development of Ghat(ChandiGhat, Haridwar) 50.36 Approved 2015-18
Bihar 1 Ganga River Front Development at Patna (EAP - World Bank) 243.27 Approved 2017-18
Total projects 273 Total Cost 9488.12