(a) whether any Audit Report has mentioned about an unproductive expenditure of Rs. 890.18
crores regarding gauge conversion of Lumding-Silchar-Giriban, Badarpur-Kumarghat Project;
(b) if so, whether the said report has also highlighted about improper planning and other
aspects regarding the said project;
(c) whether the Railways have examined the report and adopted remedial measures in compliance
to that report; and
(d) if so, the details thereof?