MINISTER OF STATE (INDEPENDENT CHARGE), MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION(SHRI G.K.VASAN)
(a) Yes, Sir.
(b) The reasons for projects running behind schedule include; lack of supporting infrastructure,
delay in award of contracts, slow progress by the contractors, delay in land acquisition and
related rehabilitation, law and order problems, fund constraints and geological surprises.
(c) Yes Sir.
(d) As on March 2008, out of 909 projects costing Rs.20 crores and above on the monitor of the
Ministry of Statistics and Programme Implementation, 346 projects are running behind with respect
to their latest approved schedule. Cost overrun in 346 delayed projects is Rs.24,689 crores which
is 13.33 percent of the latest approved cost of Rs.1,85,089 crore. The steps taken by the
Government to complete such projects include:
(i) adoption of two-stage clearance system and stricter appraisal of projects before investment
approval;
(ii) taking up of projects for implementation only after funds have been fully tied up;
(iii) in-depth review of projects on monthly and quarterly basis by the Government;
(iv) follow up with the State Governments in respect of problems relating to land acquisition,
rehabilitation related issues, forest clearances, infrastructure facilities, ensuring law and
order at project sites, etc.
(v) setting up of an Empowered Committee in the administrative Ministries for review of
departmentally executed projects;
(vi) inter-ministerial coordination for resolving unresolved problems;
(vii) setting up of Standing Committees in the Ministries/Departments to fix responsibility for
time and cost overruns;
(viii) appointment of nodal officers for each project with continuity of tenure; and
(ix) issue of guidelines on standard bidding documents for adoption.