Question : GAUGE CONVERISON IN GUJARAT



(a) the details and the present status of proposals/representations for the gauge conversion received by the Railways from Gujarat;

(b) the present status of gauge conversion of Ahmedabad-Udaipur section;

(c) the details of funds allocated/ spent thereon so far and whether the budget provision for the year 2013-14 is sufficient for the implementation of the project; and

(d) the time frame set for completion of the project?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI ADHIR RANJAN CHOWDHURY)

(a) to (d): A Statement is laid on the Table of the House.

STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 828 BY SHRI HARIN PATHAK TO BE ANSWERED IN LOK SABHA ON 08.08.2013 REGARDING GAUGE CONVERSION IN GUJARAT.

(a): Requests are received at various levels and a compendium is not maintained. However, the details of gauge conversion proposals received in recent past pertaining partly/fully in the State of Gujarat, their status and funds allocated/spent on the sanctioned projects is as under:

S. No.	Name of the proposals	Status
1.	Ahmedabad-Botad-Bhavnagar	Gauge conversion of Ahmedabad-Botad has been	included in the Budget 2012-13. The project has	been transferred to Rail Vikas Nigam Ltd. (RVNL)	for execution. Preliminary activities like	preparation of plan, estimates have been taken	up. An outlay of ` 1 crore has been provided for	this project in the Budget 2013-14. Botad-	Bhavnagar section is already in the Broad gauge	network.
2.	Dhasa-Jetalsar	The work has been included in the Budget 2012-13.	The project has been transferred to Rail Vikas	Nigam Ltd. (RVNL) for execution. Preliminary	activities like preparation of plan, estimates	have been taken up. An outlay of ` 1 crore has	been provided for this project in the Budget	2013-14.
3	Ahmedabad-Mehsana	Survey has been included in the Budget 2012-13.	Preliminary activities for taking up the survey	have been taken up.
4.	Khambhat-Khambhat Port	Survey has been included in the Budget 2012-13.	Preliminary activities for taking up the survey	have been taken up.
5.	Nadiad-Bhadran	Survey not yet taken up.
6.	Bharuch-Samni-Dahej	Conversion of this section has been completed	and commissioned. An expenditure of ` 193.04	crore has been incurred upto March, 2013. An	outlay of ` 3.73 crore has been provided for	this project in the Budget 2013-14.
7	Viramgam-Samakhiali	There is already an existing broad gauge line.	Doubling of this section has been sanctioned in	the year 2011-12. An expenditure of ` 81.00 crore	has been incurred upto March, 2013. An outlay	of ` 115 crore has been provided for this	project in the Budget 2013-14.
8.	Navlakhi-Malia-Rajkot	Already converted to broad gauge.
9.	Mehsana-Viramgam	Already converted to broad gauge.
10.	Viramgam-Surendranagar	Already converted to broad gauge. Doubling of	this section has been included in the Budget	2010-11. Work taken up. An expenditure of ` 109	crore has been incurred upto March, 2013. An	outlay of ` 130 crore has been provided for this	project in the Budget 2013-14.
11.	Mehsana-Patan	Already converted to broad gauge.
12.	Samakhiali-Gandhidham-Kandla	The section is already an existing double broad	gauge line section.
13.	Gandhidham-Anjar-Mundra	The section is already on broad gauge line. 
(b): The gauge conversion of Ahmedabad-Himmatnagar-Udaipur (299.20 km) with material modification of Shamlaji Junction-Modasa new line has been taken up. Ahmedabad-Himmatnagar and Material modification Shamlaji Jn.-Modasa is being executed by Western Railway and balance Himmatnagar- Udaipur section by North Western Railway. On Himmatnagar-Udaipur section (208.48 km) 12.72 lakh cum earthwork out of 71 lakh cum, 11 major bridges out of 45 and 24 minor bridges out of 636 have been completed. Final Location Survey for Ahmedabad-Himmatnagar section along with new line between Modasa-Shamlaji has been taken up.

(c): An expenditure of about ` 108.77 crore has been incurred upto March, 2013. An outlay of 30 crore has been provided for this project for the year 2013-14, which is insufficient for the project costing ` 1215 crore.

(d): Due to huge throw forward of ongoing projects and limited availability of resources, target date for completion of the project has not been fixed.