(a) the project-wise generation capacity of hydro electric projects run by National Hydro Power Corporation Limited (NHPC) in the country and revenue earned by the Corporation;

(b) the project-wise details of NHPC projects operated in Jammu & Kashmir with their cost of construction, generation of power and the revenue earned so far by each one of them;

(c) whether the Government of Jammu & Kashmir has made any formal request to the Union Government for the return of the Hydel projects that have earned more than their investment cost or for the re-negotiation of terms and conditions with the NHPC; and

(d) if so, the details thereof along with the reaction of the Union Government thereto?

Answer given by the minister


THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL AND NEW & RENEWABLE ENERGY ( SHRI PIYUSH GOYAL )

(a) :Details of Power Stations under Operation and the revenue earned by the NHPC Limited upto 2013-14 is as under:-

 S.No	Name of power station	Installed capacity (MW) 1	Bairasiul	180 2	Loktak	105 3	Salal	690 4	Tanakpur	120 5	Chamera -I	540 6	Uri-I	480 7	Rangit	60 8	Chamera-II	300 9	Dhauliganga	280 10	Dulhasti	390 11	Teesta V	510 12	Sewa II	120 13	Chamera-III	231 14	Chutak	44 15	TLDP-III	132 16	Nimoo-Bazgo	45 17	Uri-II	240 18	Parbati-III	520	TOTAL	4987 

(b) : At present, seven hydro electric projects with total capacity of 2009 MW are under operation in J&K. Detail of these Power projects in respect of generation of power, cost & revenue earned is as under:
 Sl.	Name of	Installed	Capital Cost	Generation No.	power	capacity	as on COD	up to the year	station	(MW)	(in Crs.)	2013-14	(MU) 1	Salal	690	981.82	74632 2	Uri-I	480	3506.0	43287 3	Dulhasti	390	5233.96	15345 4	Sewa II	120	1095.20	1911 5	Chutak	44	2156.02	60 6	Nimoo-Bazgo	45	956.39	88 7	Uri-II	240	847.49	404	Total	2009	14776.89	135727 

The information regarding Revenue Earned upto 2013-14, in case of both (a) & (b) is being compiled and will be provided after compilation.

(c) & (d) :We have not received any proposal from the Government of J&K for the return of hydel projects that have earned more than their investment cost or for the re-negotiation of terms and conditions with the NHPC.