THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL AND NEW & RENEWABLE ENERGY ( SHRI PIYUSH GOYAL )
(a) :Details of Power Stations under Operation and the revenue earned by the NHPC Limited upto 2013-14 is as under:-
S.No Name of power station Installed capacity (MW) 1 Bairasiul 180 2 Loktak 105 3 Salal 690 4 Tanakpur 120 5 Chamera -I 540 6 Uri-I 480 7 Rangit 60 8 Chamera-II 300 9 Dhauliganga 280 10 Dulhasti 390 11 Teesta V 510 12 Sewa II 120 13 Chamera-III 231 14 Chutak 44 15 TLDP-III 132 16 Nimoo-Bazgo 45 17 Uri-II 240 18 Parbati-III 520 TOTAL 4987
(b) : At present, seven hydro electric projects with total capacity of 2009 MW are under operation in J&K. Detail of these Power projects in respect of generation of power, cost & revenue earned is as under:
Sl. Name of Installed Capital Cost Generation No. power capacity as on COD up to the year station (MW) (in Crs.) 2013-14 (MU) 1 Salal 690 981.82 74632 2 Uri-I 480 3506.0 43287 3 Dulhasti 390 5233.96 15345 4 Sewa II 120 1095.20 1911 5 Chutak 44 2156.02 60 6 Nimoo-Bazgo 45 956.39 88 7 Uri-II 240 847.49 404 Total 2009 14776.89 135727
The information regarding Revenue Earned upto 2013-14, in case of both (a) & (b) is being compiled and will be provided after compilation.
(c) & (d) :We have not received any proposal from the Government of J&K for the return of hydel projects that have earned more than their investment cost or for the re-negotiation of terms and conditions with the NHPC.