Question : RAILWAY PROJECTS IN MADHYA PRADESH



(a) the details of railway projects received from Madhya Pradesh during the last three years, year-wise;

(b) the steps taken on each of the proposals and the reasons for non-approval of the projects, if any;

(c) the details of present status of on-going railway projects/surveys along with the estimated cost thereof;

(d) the expenditure incurred on each project alongwith the allocations made to each project during the said period and the current year;

(e) the reasons for the slow progress in regard to completion of these projects; and

(f) the time by which these projects are likely to be completed?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)



(a) to (f) : A Statement is attached.


STATEMENT REFERRED TO IN REPLY TO PARTS (a) to (f) OF LOK SABHA UNSTARRED QUESTION NO. 4870 BY SHRI KANTILAL BHURIA AND DR. CHARAN DAS MAHANT TO BE ANSWERED ON 19.04.2001 REGARDING RAILWAY PROJECTS IN MADHYA PRADESH

(a) & (b) : Planning of Railways services or projects is made keeping a national perspective in view and taking an integrated view of traffic demands as well as of System requirements. Geographical boundaries of a state do not form a criterion for taking investment decisions. However, proposals relating to Railway projects, received from the Government of Madhya Pradesh in the last three years and action taken thereon are given below:-

Year Proposal Action Taken
1998- Expediting the execution of : 99 Bilaspur- Final location survey for Bilaspur to Urkura : 3rd Bhatapara has been completed. Contracts Line for bridges and ballast have been awarded.Work of earthwork,minor bridges and ballast are in progress. Akaltara- Akaltara-Naila-Hasdeo (23 km) completed, Champa : 3rd except the Hasdeo bridge which will be Line completed during 2001-02. Urkura- Work completed and commissioned. Raipur- Sarona : Doubling 1999- New Line This work has been included in the 2000 from Ramganj Railway Budget 2000-01. Final Location Mandi to Survey under progress and will be Bhopal. completed by June 2001. New Line Government of MP has been approached for from Khandwa financing the proposed line. to Dahod 2000- Expediting Final location survey from Gondia to 01 the Gauge Balaghat including Balaghat-Katangi has Conversion been completed including geo-technical of Jabalpur- investigations of major bridges. The Gondia, survey between Balaghat-Jabalpur is in including progress. Land has been acquired upto Balaghat- Balaghat. Formation work, bridge work and Katangi ballast supply are in progress between Gondia and Balaghat.
(c) to (f) : Details of all ongoing Railway projects presently in Madhya Pradesh, including their estimated cost, expected expenditure likely to be incurred on each project upto March 2001, allocations made in each of the last three years, outlay proposed for 2001-02 and target wherever fixed along with reasons for slow progress, if any are at Appendix-I
Details of ongoing surveys presently in Madhya Pradesh are at Appendix-II. Approximate cost of the projects will be known after the completion of the surveys.

APPENDIX – I APPENDIX REFERRED TO IN REPLY TO PARTS (c) TO (f) OF LOK SABHA UNSTARRED QUESTION NO. 4870 FOR 19.04.2001 S. Name of Latest Outlay Budget Budget Budget Budget Status No. Project Antici- expected Outlay Outlay Outlay Outlay pated to end for 1998-for 1999-for 2000-Proposed Cost of 2000- 99 2000 01 for 2001- 01 02

(Amount in Crores of Rupees)
ON-GOING RAILWAY PROJECTS IN MADHYA PRADESH
New Lines
1 Guna- 337.33 275.33 21.50 18.00 25.00 25.00 Guna-Gwalior and Gwalior Etawah - Soni sections have already been completed. The next phase work of Gauge Conversion between Soni and Bhind is in progress where earthwork, bridges and ballast collection have been taken in hand.The last phase of this project from Bhind to Etawah involves construction of 3 major bridges on the rivers Chambal, Kunwari and Yamuna. The work on Yamuna Bridge has already been taken up and sinking of wells is the progress. Tender for work of Chambal bridge has been invited.The work will be completed in the coming years as per availability of resources. 2 Lalitpur- 925.00 6.22 1.00 5.00 5.00 5.00 Necessary clearances have Satna & been obtained. Final Rewa- location survey for 100 Singrauli km from Lalitpur end and 64 km from Mahoba to Khajuraho and 22 km from Rewa toward Singurali has been completed and Final Location Survey for balance section is in progress. Papers for land acquisition are under preparation. 3 Godhra- 597.00 25.18 5.00 4.00 10.00 15.00 This work is being Indore- executed in phases. The Dewas- first phase work between Maksi Dewas & Maksi is now in progress. Work is in progress on 2 major bridges remaining 6 major bridges have been completed . Work on all 49 minor bridges have been completed. The ballast supply is in progress. This sub section is targetted during 2001-02. Work on Phase-II from Godhra to Indore will be taken up after Phase-I get completed. 4 Ramganjman 425.00 0.05 … … 1.00 5.00 Final location survey is di-Bhopal is under progress and will be completed by June 2001.
Gauge Conversion
5 Jabalpur- 386.30 16.02 20.00 22.00 16.80 15.00 Final location survey Gondia from Gondia to Balaghat including including Balaghat- Balaghat- Katangi has been Katangi completed including geo- technical investigations of major bridges. The survey between Balaghat- Jabalpur is in progress. Land has been acquired upto Balaghat. Formation work, bridge work and ballast supply are in progress between Gondia and Balaghat. 6 Neemuch- 116.74 14.81 10.00 5.00 5.00 15.00 Work on long lead items Ratlam has been taken up. Strengthening of Substructure on all 31major bridges have been completed. Strengthening of substructure on 110 out of 123 minor bridges have been completed.Superstructure of 6 major and 94 nos minor Bridges also have been completed. The work will be progressed and completed in the coming years as per availability of resources.
Doubling
7 Kalapipal- 53.00 0.01 0.01 0.01 0.10 1.00 This work has been Phanda/ temporarily frozen Maksi- owing to low operational Bhopal priority and constraint of resources. 8 Bolai- 94.39 51.88 10.00 10.00 16.00 0.10 Work has been completed Kalisindh, and commissioned. Kalisindh- Kisoni, Kisoni- Bercha & Maksi- Pirumrod


APPENDIX - II APPENDIX REFERRED TO IN REPLY TO PARTS (c) TO (f) OF LOK SABHA UNSTARRED QUESTION NO. 4870 FOR 19.04.2001
S. Name of the Project Plan-Head Status No.
ON-GOING RAILWAY SURVEYS IN MADHYA PRADESH
1 Pulgaon-Arvi GC with extn. to Gauge Conversion Survey is in Amla progress. 2 Chhindwara – Nagpur Gauge Conversion Survey is in progress. 3 Chhindwara-Nainpur Gauge Conversion Survey is in progress. 4 Pratapnagar to Chhota Udaipur Gauge Conversion Survey is in Gauge conversion and new BG progress. line from Chhota Udaipur to Dhar 5 Bad-Bhainsa New Line Survey is in progress. 6 Jabalpur to Panna via Damoh New Line Survey is being taken up. 7 Jalna-Khamgaon New Line Survey is in progress. 8 Khandwa to Nardana via New Line Survey is in Khargone, Sendhwa progress. 9 Shirpur-Mhow New Line Survey is in progress. 10 Bilaspur to Jabalpur. New Line Survey is in progress. 11 Bisrampur to Jabalpur New Line Survey is in progress. 12 Katangi to Tirodi New Line Survey is in progress. 13 Rajnandgaon-Jabalpur New Line Survey is in progress. 14 Ramtek to Gotegaon via New Line Survey is in Khawasa, Seoni and Dhuma progress. 15 Chota Udaipur - Dhar New Line Survey is in progress. 16 Dungarpur to Ratlam via New Line Survey is in Banswara progress.