Question : OUT OF ORDER SOLAR TELEPHONHES



(a) Whether the Government are aware that 99 percent Solar Telephone (run by solar energy) are lying out of order in Yavatmal district of Maharashtra ;

(b) if so, the reasons therefore ;

(c) the time by which these telephones are likely to be rectified ; and

(d) the investment made so far by the Government on these telephones ?

Answer given by the minister


MINISTER OF STATE FOR COMMUNICATIONS (SHRI TAPAN SIKDAR)


(a) No Sir. The percentage of faulty VPTs in Yavatmal district is 10%. The status is as follows:-

Total MARR VPTs	:	844	Faulty VPT	: 86	% of faulty VPT	: 10.18%
(b)
(i) Improper keeping up of equipment by local VPT Holders.
(ii) Worn out batteries.
(iii) Broken solar panels.
(iv) Limited availability of Card repair facility.

(c) The faulty VPTs on MARR will be rectified within 3 months.

(d) The total investment made in Yavatmal district on MARR VPTs is approximately 8 crores.