MINISTER OF STATE IN THE MINISTRY OF CHEMICALS AND FERTILIZERS
(SHRI RAMESH BAIS)
(a) to (d): Government had constituted a Core Group to explore the possibility of
import of LNG for manufacture of fertilizers. The Core Group submitted its report to the
Government in March 1999. The highlights of the project, as recommended by the Core
Group are given below:-
(i) A 7 million tonne per annum LNG project, basically for fertiliser feedstock but
could also serve complementary sectors like power, domestic gas etc., to be
implemented in two phases.
(ii) It is proposed to implement the project as an integrated chain with overseas
liquefaction plant, LNG tankers, a regasification terminal and the gas delivery
system with pipelines and compressors.
(iii) The suggested location of the regasification terminal was Kishorprasad in Orissa.
(iv) The cost of the project has been estimated at Rs. 21832 crore and a completion
schedule of seven-and-half years for both the phases.
Based on the recommendations of the Core Group, the proposal for preparation of
Detailed Feasibility Report on the project at an estimated cost of Rs. 25 crore to
be funded by the Consortium of various companies is being processed by the
Government.
(e) The revamp of Namrup unit of Hindustan Fertilizer Corporation Ltd. (HFC) is
already under implementation. The rehabilitation of the remaining units of HFC and
various units of Fertilizer Corporation of India Ltd. would depend on the decision of the
competent authority in the Government and the final sanction of the Board for Industrial
and Financial Reconstruction.