(a) whether the two-way system project is going on National Highways in West Bengal ;
(b) if so, the total cost thereof ;and
(c) the time by which the project is likely to be completed?
(a) whether the two-way system project is going on National Highways in West Bengal ;
(b) if so, the total cost thereof ;and
(c) the time by which the project is likely to be completed?
MINISTER OF STATE IN THE MINISTRY OF SURFACE TRANSPORT
(Dr. DEBENDRA PRADHAN)
(a) to (c) Yes Sir, two project of widening to four lanes of National Highway 2 in West
Bengal are in progress between Barakar - Raniganj and from Raniganj -Panagarh which were sanctioned for Rs.231.62 Crore. The project are targetted for completion in October, 2000 and January, 2001 respectively.