THE MINISTER OF WATER RESOURCES (SHRI PRIYA RANJAN DASMUNSI)
(a) to (f) A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (A) TO (F) OF LOK SABHA
STARRED QUESTION NO.93 FOR ANSWER ON 12-07-2004 REGARDING PENDING
IRRIGATION PROJECTS
(a) to (f) The Ministry of Water Resources/Central Water
Commission and Planning Commission reviews the status of on-
going/pending irrigation projects of the states from time to time
with the representatives of the State Governments. The Central
Water Commission is regularly monitoring selected on going major and
medium irrigation projects.
The State-wise details of major and medium irrigation projects
lying pending with the Central Water Commission for techno-economic
appraisal are given in the Annexure - I. The common reasons for
delay in clearance of major and medium irrigation projects are
inadequate technological studies, irrigation planning, estimate and
economic analysis, lack of attention to international and inter-
State aspects, conjunctive use of surface and ground water,
concurrence of state finance, absence of environmental and forest
clearances, clearances of resettlement & rehabilitation plans, etc.
while submitting detailed project report to Central Water
Commission. The clearance of projects depends upon the promptness
with which the State authorities arrange the compliance to the
observations of the Central appraising agencies.
Concerned with a large number of major and medium irrigation
projects spilling over into Ninth Five Year Plan, the Central
Government launched the Accelerated Irrigation Benefits Programme
(AIBP) during 1996-1997 for accelerating implementation of such
ongoing irrigation/multi-purpose approved projects on which
substantial progress has been made and which are beyond the resource
capability of the State Governments. The Central Loan Assistance
(CLA) under AIBP is released to the State Government on an year to
year basis as per the ceiling fixed by the Planning Commission and
this ceiling is finalised in the annual plan discussion held between
the Planning Commission and State Government. An amount of Rs.
14,670 crore has, so far, been released as CLA under the programme
for 181 major/medium and 3810 surface Minor Irrigation Schemes. The
details of CLA under AIBP is given in the Annxeure II.
ANNEXURE-I
Statement referred to in reply to Lok Sabha Starred Question No. 93 to be answered on 12.7.2004
regarding Pending Irrigation Projects.
STATE WISE LIST OF NEW PROJECrs UNDER APPRAISAL
Sl. Name of Projects Name of Major/ Date of Estt. Cost Category
No. State Medium Receipt (Cr.)
1 Nettampadu Lift Irriltation Scheme Andhra Pradesh Maior 11/2000 134:30 A
2 Kalwa Kurthi Lifi Irriltation Scheme Andhra Pradesh Maior 11/2000 380.00 A
3 Thotapallv Barralte . Andhra Pradesh Maior 9/200 I 415.87 B
4 Pulichintala Irrigation Project Andhra Pradesh Major 7/93 506.20 B (Masonry Dam)
5 Krishna Delta System Modernisation Andhra Pradesh Major 1/96 659.16 B ERM
6 Bhima Lift Irriltation Andhra Pradesh Maior 1/96 744.00 B
7 Sriramsagar Stage-II Andhra Pradesh Major 2 697.70 B
8 Flood Flow Canal from SRSP Andhra Pradesh Maior 12/93 1331.00 B
9 Jurala (Masonrv Dam) Andhra Pradesh Major 9/80 545.2 B
10 Vamsadhara Project Andhra Pradesh Major 5/83 275.74 B Stage II # (86-87 SOR) (Neradi Barrage)
11 Musurumilli Reservoir Project Andhra Pradesh Medium 3/2003 167.35 A
12 Gollavagu Reservoir# Andhra Pradesh Medium 6/2001 39.58 A
13 Rallivagu Reservoir Andhra Pradesh Medium 9/200t 26.75 A
14 Nilwai Reservoir Andhra Pradesh Medium 9/2001 48.90 A
15 Appraisal of Mathadivagu reservoir Anqhra Pradesh Medium 05/2002 26.44 A project
16 Janjhavathi Project# Andhra Pradesh Medium 01/2002 121.0 A
17 Pdagedda Reservoir Project. Andhra Pradesh Medium 01/2002 32.117 B
18 Pedderu Reservoir Andhra Pradesh Medium 9/91 26.23 B
19 Palemvagu Andhra Pradesh Medium 5/88 29.13 B (Masonry Dam).
20 Valligallu Reservoir Andhra Pradesh Medium 02/2000 143.67 B
21 Yerravagu Andhra Pradesh Medium 3/99 31.28 B (Earthen Dam)
22 Suddavagu Andhra Pradesh Medium 3/99 56.48 B (Earthen Dam)
23 Peddavagu Andhra Pradesh Medium 8/99 202.60 B (Earthen Dam).
24 Surampalem Res. Scheme Andhra Pradesh Medium 10/99 46.70 B (Earthen Dam)
25 Surampalem Andhra Pradesh Medium 7/2000 49.50 B Phase-II.
26 Bhupatipalem Andhra Pradesh Medium 7/2000 47.23 B (Dam)
27 Kadwan Reservoir Project Bihar Major 5/98 1111.14 A
28 Upper Mahananda Irrigation Scheme Bihar Maior 5/2000 124.00 A
29 Punpun Barra2e Bihar Major 5/2000 102.26 B
30 Tilaiva Dhadhar Bihar Mlijor 1/98 220.1I B
31 KeJo Irrigation Project Chhattisgarh Major 9/2003 235.00 A (Masonarv Dam)
32 Mongra Irrigation Project Chhaltisgarh Medium 3/03 83.46 B
33 Suliapat Reservoir Proiect- Chhaltisgarh Medium 9/02 40.09 D
34 Modemisation ofMachchu-l-ERM Gujarat Major 2/91 8.12 B
3S Western Yamuna Link Channel Haryana Major 12/96 31.26 B
36 Satluj Yamuna Link Canal Haryana Major 10/93 61.76 B
37 Khet Purali Dam Project Haryana Medium 12/95 16.92 A (Earthen Dam)
38 Renuka Dam Himachal Pra Major 8/97 1224.64 B (Multipurpose)
39 Balh Valley Left Bank Irrigation Proj. Himachal Pra Medium 8/99 41.64 B
40 Phina Singh Himachal Pra Medium 10/2003 63.00 A
41 Tawi Pump House and Tawi Lift Canal - J&K Major 9/2001 13.563 A ERM (Kashmir Region)
42 Mod. of Nandi Canal- ERM J&K Medium 5/99 6.61 A (Kashmir Region)
43 Mod. of Ahji Canal -ERM J&K Medium 04/2000 7.96 A (Kashmir Region)
44 Mod. of Lar Canal -ERM J&K Medium 4/2000 6.63 A (Kashmir Region)
45 MOd. Of Mavkhul - ERM J&K Medium 12/97 7.00 A (Kashmir Region)
46 Mod. Of Martand Canal -ERM J&K Medium 12/97 17.72 A (Kashmir Region)
47 Mod. of Babul Canal- ERM J&K Medium 6/99 4.77 A (Kashmir Region)
48 Kandi Canal Project J&K Medium 4/2002 37.31 A (Kashmir Region)
49 Modemisation of Dadi Canal - ERM J&K Medium 6/99 11.10 B (Kashmir Region)
50 Modemisation of New Pratap Canal - J&K Medium 12/99 21.68 B ERM (Jammu Region)
51 Mod. of Kathua Canal- ERM J&K Medium 9/99 15.68 B (Jammu Region)
52 Kanhar Reservoir Proiect Jharkhand Maior 11/98 1015.76 A
53 North Koel Reservoir Jharkhand Maior 5/99 836.11 A
54 Upper Sakri Reservoir Jharkhand Major 1/98 437.94 A
55 Punasi Reservoir Jharkhand Maior 7/92 221. 65 B
56 Subemakha (Multipurpose) - Proiect Jharkhand Major 8/89 1428.82 B
57 Ajoy BarragelSiktia Barrage Jharkhand Major 3/98 248.10 B
58 Konar Irrigation Jharkhand Major 7/99 336.69 B
59 Singatalur Karnataka Major 7/98. 123.00 A (Huligudda) Lift Irrigation Scheme
60 Markandeya Kamataka Major 5/97 209.85 8
61 Hippargi Irrigation Project (Earthen Kamataka Major 8/85 186.70 B Darit) .
62 Upper Tunga Project Kamataka Major 2/92 1052.33 B
63 Basapur Lift Irrigation Scheme Kamataka Medium 11/96 9.36 A
64 Idmalayar Irrigation Project Kerala Major 2/92 107.00 B (Barrage, Earthen Dam with Canal system on both bank)
65 Attapady Irr. Project -Masonary Dam Kerala Medium 3/96 110.00 A with vertical lift type spillway,canal SYStem on both banks)
66 Halon Irrigation Project Madhya Pradesh Major 1/2000 193.01 A (Earthen Dam)
67 Punasa Lift Irrigation Madhya Pradesh Mllior 3/2003 157.00 A
68 Upper Narmada Madhya Pradesh Major 9/96 345m A
69 lower Goi Madhya Pradesh Maior 07/2003 164.93 A
70 Kolar Project (Earthen Dam) Madhya Pradesh Mitior 10/91 139.14 B
71 Thanwar Tank (Earthen Dam) Madhya Pradesh Mllior 12/89 24.38 B
72 Pench Diversion (Earthen Dam) Madhya Pradesh Major 8/88 184.04 B
73 Rajghat Canal Madhya Pradesh Major 2/90 309.21 D
74 Bhanpura Canal Scheme Madhva Pradesh Medium 12/2002 59.49 A
75 Human River Project Maharashtra Major 1/2002 423.47 A (Earthen Dam)
76 Lower Wardha Maharashtra Maior 11/97 61. 99. A (Earthen Dam)
77 Lendi Irrigation Project-Joint venturc Maharashtra Major 6/01 275.84 A of Maharashtra Md A.P. (Earthen Darn)-
78 Sina Kolegaon Maharashtra Maior 3/03 317.77 A
79 Sulwade-Jamphal-Kanoli LIS Maharashtra Maior 11/2003 788.89 A
80 Sangola Branch Canal Maharashtra Maior 2/86 37.01 A
81 Tarali Maharashtra Major 7/02 504.96 B
82 Warna Irrigation Maharashtra Major 8/83 337.81 B (Earthen Dam)
83 Arunavati River Project Maharashtra Major 12/87 66.48 B (Earthen Dam)
84 Punad Irrigation Maharashtra Major 3/89 29.22 B (Composite Dam)
85 Lower Wunna Project Maharashtra Major 2/89 87.55 B (Earthen Dam)
86 Talamba Irrigation Project Maharashtra Major 6/92 289.09 B (Earthen Dam)-
87 Dhom Balakwadi Maharashtra Major 7/02 475.29 B
88 Gunjawani Maharashtra Major 5/98 364.63 C (Earthen Dam)
89 Bhama Askhed Maharashtra Major 9/01 455.05 C
90 Nira Deoghar Maharashtra Maior 7/02 870.04 C
91 Urmodi Maharashtra Maior 7/02 866..59 C
92 Sulwade Barrage Maharashtra Medium 12/97 88.25 A
93 Shelgaon Maharashtra Medium 3/02 198.06 A
94 Prakasha Barrage Maharashtra Medium 4/99 93.60 A
95 Jambre Maharashtra Medium 7/99 50.70 A (Earthen Dam)
96 Andhra Khore Maharashtra Medium 2/2000 44.37 A (Masonry Dam)
97 Sapan (Medium) Maharashtra Medium 9/2000 36.30 A (Earthen Dam)
98 Srangkheda Maharashtra Medium 10/2000 132.51 A (Earthen Dam)
99 Haranghat L.I.S. Maharashtra Medium 11/2000 44.11 A
100 Gul River Maharashtra Medium 11/2000 55.94 A (Earthen Darn)
101 Ghataprabha Maharashtra Medium 1/01 34.92 A (Earthen Dam)
102 Koradinalla Maharashtra Medium 3/01 17.32 A (Earthen Dam)
103 Dam Maharashtra Medium 3/01 32.62 A (Earthen Dam)
104 Nagan Maharashtra Medium 3/01 48.38 A (Earthen Dam)
105 Northmand Maharashtra Medium 4/01 93.00 A (Earthen Dam)
106 Wang Maharashtra Medium 4/01 134.39 A (Earthen Dam)
107 Kamani Tanda Maharashtra Medium 7/01 42.22 A
108 Pimple Goon Maharasbtia Medium 2/02 (Ori.) 7.39- A Latest 42.78
109 Ambeohol (Hiranyakeshi) Maharashtra Medium 6/02 50.65 A
110 Chandrabhaga Maharashtra Medium 7/93 35.30 A
III Lower Panzara Maharashtra Medium 3/01 45.24 A
112 Shivan Maharasbtra Medium 11/02 28.89 A
113 Wadi-Sbewadi Maharashtra Medium 11/02 98.44 A
114 Amravati Maharasbtra Medium 12/02 48.34 A
lIS Jamkhedi Maharashtra Medium 11/02 31.28 A
116 Kudali Maharashtra Medium 12/02 262.20 A
117 Sarf Nalla Maharashtra Medium 12/02 46.56 A
118 Wagholi Buti Lift Maharashtra Medium 3/03 24.98 A
119 Pothra Nalla Maharashtra Medium 5/98 63.08 B (Earthen Dam)
120 Chilhewadi Maharashtra Medium 7/02 146.24 B
121 Wakod Maharashtra Medium 3/2000 34.36 B (Earthen Dam)
122 Lal Nala Maharashtra Medium 9/97 43.61 B (Earthen Dam)
123 Raigavan Maharashtra Medium 12/93 9.51 B (Earthen Dam)
124 Jam Irrigation Maharashtra Medium 5/94 42.63 B (Earthen Dam)
125 Kar Maharashtra Medium 4/95 44.71 B (Composite Dam)
126 Utwali Maharashtra Medium 11/95 35.77 B (Earthen Dam)
127 Jangam Hatti Lift Irrieation Maharashtra Medium 6/98 4.29 B
128 Tipai Mukh Dam Project Manipur Major 2/95 2899 B (Multi-purpose) (Earth & Dock fill Dam)
129 Jiri Irrigation Manipur Medium 10/97 48.68 D (Barrage)
130 Dikhu MultiDurpose Project Nagaland Maior 4/02 999.7 A
131 D`zuza Irrigation Project (Barrage) Nagaland Medium 5/98 49.0 B
132 Improvement to Taladanda Canal and Orissa Major 8/99 57.06 A Distributory No. 12 with its system- ERM#
133 Drainage Dev. Phase-I under Mahanadi Orissa Major 2/2000 227.75 A Delta Stage-I & II - ERM#
134 Master Plan for Drainage Development Orissa Major 11/2003 570.77 A in Coastal Belt of Orissa
135 Upper Kolab Extension Project-ERM# Orissa Major 9/98 71.66 B
136 Ib Irrigation Project Orissa Major 2/98 1140 B Composite Rockfill Dam with concrete spillway canals on both right & left banks.
137 Ong Dam Project Orissa Major 3/97 304.66 B (Earthen Dam with Ogee type radial gated spillway, canal system, on both right left banks)
138 Brutang Irr. Project Orissa Major 1/98 227.25 B (Earthen Dam with concrete spillway, Link canal to Kuanaria Reservoir, Main Canal on right bank of Kuanaria reservoir)
139 Anandpur Barrage Project Orissa Major 1/2001 482.26 B
140 Upper Udanti lrriRation Proiect Orissa Medium 02/2003 68.37 A
141 Mahendratanaya Irrigation Project Orissa Medium 3/2000 100.98 B (Dam)
142 Manjore (Earthen Dam with Ogee type Orissa Medium 8/91 37.70 B spillway, canal system on right and left bank)
14.3 Rukura (Earthen Dam with Ogee type Orissa Medium 5/93 15.15 B spillway, canal system on right and left banks).
144 Dhauragoth (Earthen Dam with Central Orissa Medium 9/96 16.80 B Ogee type radial gated spillway, canal system on both rieht & left banks)
145 Upper Lanth (Earthen Dam with Central Orissa Medium 11/97 48.99 B Ogee type radial gated spillway, canal system on rieht bank)
146 Samakoi Orissa Medium 2/99 43.85 B (Barrage)
147 Hadua/Mahanadi Irrigation Project Orissa Medium 2/2001 61.48 B (Earthen Dam)
148 Punjab Irrigation & Drainage Project Punjab Major 5/98 1149.00 A (Phase III)#
149 Sri Dashmesh Irrigation Proiect Punjab Maior 2/2001 647 A
150 Raising lining of Bhakra Main Canal- Punjab Major 3/02 26.69 A ERM
151 Modified Project estimate of SYL canal Punjab Major 6/94 195.44 A Part-III#
152 SYL Main Canal Part-I# Punjab Major 09/94 60125 D
153 Raising of Lining /Bank of Sirhind Punjab Medium 5/2001 13.7543 A Feeder - ERM
154 Rehabilitation of Channels of ISI Punjab Medium 5/2001 46.00 A Patiala Feeder and Kotla Branch
155 Punjab Irrigation Project (Lining of Punjab Medium 2/2000 49.02 B Channels) under RIDF fund-ERM (9/99 Price Level)
156 Pipalda Lift Irrigation Rajasthan Major 9/96 11.39 A
157 Indira Lift Irrigation Scheme Raiasthan Major 12/2003 431.00 A
158 Utilisation of Yamuna water in Rajasthan Major 7/96 150.00 B Bharatour Distt.
159 Utilisation of Yamuna water in Rajasthan Major 1/98 273.00 B Jhunihunu & Churu Distt.
160 Indira Gandhi Rajasthan Major 3/93 121. 92 B Nahar Stage-I -ERM#
161 Rajasthan Water Sector Restructuring Rajasthan Major 1/01 745.59 B Proiect - ERM#
162 PiDlad Irri2alion (Dam) Raiasthan Medium 2/93 21.88 A
163 Chakan Irrigation Rajasthan Medium 9/92 9.55 B (Dam)
164 Grarda Irrigation (Dam) Rajasthan Medium 7/95 39.51 B
165 Modemisation of Cauvery Delta Phase-l Tamil Nadu Major 8/85 78.80 B - ERM#
166 Irrukkangudi Reservoir Tamil Nadu Medium 2/95 72.00 B (Earthen Dam)
167 Kanhar Irrigation Uttar Pradesh Maior 6/99 341.45 A
168 Kachnoda Dam Uttar Pradesh Major 11/2000 70.45 A
169 Improving Water Management on Uttar Pradesh Major 7/2001 102.41 B Existing Sarda Canal Svstem- ERM#
170 Bansagar Canal Uttar Pradesh Maior 2/2002 620.80 B
171 Modemisation of Lachura DamERM Uttar Pradesh Maior 4/2002 94.18 B
172 Raisin!! of Meia Dam -ERM Uttar Pradesh Maior 3/92 65.0 B
173 Maudaha Dam Uttar Pradesh Maior 3/90 125.16 B
174 Chittaurgarh Uttar Pradesh Maior 10/93 36.70 B
175 Lining of Channel in Bundelkhand Uttar Pradesh Major 5/92 57.37 B ERM
176 Increasing Capacity of Bhupali Pump Uttar Pradesh Major 8/97 60.53 B Canal-ERM
177 Uttar Pradesh Water Restructuring Uttar Pradesh Major 4/2001 663.41 B Project# (Provisional)
178 Bhaunrat Cum Utan Dam Uttar Pradesh Medium 9/2001 52.10 A
179 Kishau Darn Uttaranchal Major 7/97 4099.00 C (Maior)
180 Mod. ofKangsabati Reservoir (Phase-I) West Bengal Major 10/96 471.90 A ERM#
STATUS:
A - PROJECT UNDER VARIOUS STAGES OF APPRAISAL. B - ACCEPTED BY THE ADVISORY COMMITTEE OF MOWR SUBJECT TO CERTAIN OBSERVATIONS. C - DEFERRED BY ADVISORY COMMITTEE OF MOWR. D - RECOMMENDED TO PLANNING COMMISSION FOR INVESTMENT CLEARANCE.
ANNEXURE-II
STATEMENT REFERRED TO IN REPLY TO LOK SABHA STARRED QUESTION NO. 93 TO BE ANSWERED ON 12.7.2004
REGARDING PENDING IRRIGATION PROJECTS
CENTRAL LOAN ASSISTANCE RELEASED UNDER AIBP FROM 1996-97 TO 2003-04
(Rs. crore)
S.No. State Total
1 Andhra Pradesh 869.331
2 Arunachal Pradesh 51.500
3 Assam 120.1933
4 Bihar 425.515
5 Chhattisgarh 265.280
6 Gaa 130.400
7 Gujarat 3622.422
8 Haryana 70.235
9 Himachal Pradesh 66.648
10 Jammu & Kashmir 84.054
11 Jharkhand 66.248
12 Karnataka 1954.218
13 Kerala 89.090
14 Madhya Pradesh 1505.003
15 Maharashtra 603.384
16 Manipur 108.750
17 Meghalaya 15.264
18 Mizoram 14.916
19 Nagaland 23.389
20 Orissa 898.250
21 Punjab 415.470
22 Rajasthan 1140.394
23 Tripura 109.219
24 Tamilnadu 20.000
25 Uttar Pradesh 1788.375
26 Uttaranchal 50.715
27 West Bengal 156.710
28 Sikkim 5.260
Total 14670.233