THE MINISTER OF STATE OF HEAVY INDUSTRY AND PUBLIC ENTERPRISES
( SHRI P. RADHAKRISHNAN )
(a)& (b): A statement is laid on the Table of the House
Statement referred to in reply to Lok Sabha Unstarred Question No. 54 for answer on 7.7.2014 regarding renewable energy projects by PSEs.
(a) As per available information, details of renewable energy projects set up or proposed to be set up by the Central Public Sector Enterprises (CPSEs) is as follows:
1. The details of Grid – connected Solar Power Projects set up or proposed to be set up the Central Public Sector Enterprises (CPSEs) under Phase I and Phase-II of Jawaharlal Nehru National Solar Mission are as under:-
Sl.No Name of the Company Location Capacity Status
1 Indian Oil Corporation Rajasthan 5 MW Commissioned Limited (IOC) in 2011-12 2 GAIL (India) Limited (GAIL) Rajasthan 5 MW Commissioned in 2012-13
2. Other Solar Power Projects
Sl.No Name of the Company Location Capacity Status 1 North Eastern Electric Power Surajamoninagar 5 MW Under Installation Corporation Ltd. (NEEPCO) ,Tripura 2 NEEPCO Assam 2 MW Proposed to be set-up 3 NEEPCO Monarchak 5 MW Under Construction Tripura 4 NEEPCO Madhya Pradesh 50 MW Future Project 5 NEEPCO Assam 70 MW Future ProjectLtd. 6 National Aluminium Company Bhubaneswar 160 KW Commissioned (NALCO) 7 NALCO Bhubaneswar 100 KW Under Installation 8 National Fertilizers Ltd. (NFL) Noida 100 KW Proposed 9 NTPC Ltd. Noida 180KW Proposed 10 NTPC Ltd. Dadri, UP 5 MW Commissioned project 11 NTPC Ltd. Port Blair, A&N 5 MW Commissioned project 12 NTPC Ltd. Ramagundam, 10 MW Commissioned project Telangana 13 NTPC Ltd. Unchahar, UP 10 MW Commissioned project 14 NTPC Ltd. Talcher, Odisha 10 MW Commissioned project 15 NTPC Ltd. Rajgarh, MP 50 MW Commissioned project 16 NTPC Ltd. Faridabad, 5 MW Commissioned project Haryana 17 NTPC Ltd. Singrauli, 15 MW Under Construction 18 Neyvelli Lignite Corporation Chennai 150 MW Proposed Ltd. (NLC) 19 NLC Rajasthan 10 MW Feasibility report under preparation 20 NLC Neyveli 10 MW Under erection 21 Mahanadi Coalfield Ltd. (MCL) Odisha 2 MW Work order issued 22 Central Mine Planning & Ranchi 250 KW Proposed Design Inst. Ltd.(CMPDL) with Gujarat Energy Research Management Institute 23 Coal India Ltd. Kolkata 140 KW Completed 24 Rajasthan Electronics & Jaipur 25 KW Commissioned Instruments Ltd. (REIL) 25 Engineers India Ltd. (EIL) Gurgaon 90 KW Commissioned 26 EIL Delhi 3 KW Commissioned 27 EIL Delhi 1.2 KW Commissioned 28 EIL Chennai 35 KW Under Commissioning 29 Bharat Heavy Electrical Ranipet 5 MW Commissioned Ltd. (BHEL) 30 BHEL Ranipet 17.5 KW Commissioned 31 BHEL Bhopal 250 KW Commissioned 32 BHEL Hyderabad 250 KW Commissioned 33 BHEL Hyderabad 13.7 KW Commissioned 34 BHEL Hyderabad 13.5 KW Commissioned 35 BHEL Bangalore 42 KW Commissioned 36 BHEL Trichy 20 KW Commissioned 37 Chennai Petroleum Manali 11 KW Commissioned Corporation Ltd. (CPCL) 38 CPCL Tamil Nadu 15 MW Proposed to be set up in 2014-15 39 Steel Authority of India Bhilai 370 KW Being Set-up Ltd. (SAIL) 40 SAIL Rourkela 1 MW Being Set-up 41 Bharat Petroleum Kerala 25 KW Commissioned Corporation Ltd. (BPCL) 42 BPCL MMBPL 157 KW Commissioned 43 BPCL Not finalised 5 MW Proposed 44 Oil India Ltd. (OIL) Assam 100 KW Commissioned 45 OIL Rajasthan 100 KW Commissioned 46 OIL Rajasthan 5 MW Commissioned